Incomplete Work Submission

A · Action Individual
http://proethica.org/ontology/case/85#Incomplete_Work_Submission
Definition

Engineer A decided to submit drawings and specifications that he knew to be incomplete by the specified deadline, citing time pressure as justification, rather than requesting an extension or otherwise seeking relief from the schedule constraint.

Properties
Instance of
Action
http://proethica.org/ontology/core#Action
Event Role Context
Design Engineer
Foreseen Unintended Effects
Risk of increased project costs
Submission of documents insufficient to support construction
Guided By Principle Text
Completeness of professional deliverables
Honest representation to client
Public fund stewardship
Has Agent
Engineer A
Has Mental State
deliberate
Initiates Text
Incomplete Documents in Circulation
Public Safety Risk Latent
Unjustified Expenditure of Public Funds Risk
Intended Outcome
Meet the contractual delivery deadline and avoid conflict with the client over schedule
Requires Capability Text
Conformance with applicable engineering standards
Dam design to completion
Scheduling judgment to flag infeasible deadlines
Temporal Extent
instant
Temporal Marker
Design phase, at the deadline for deliverable submission
Temporal Sequence
5
Violates Obligation Text
Obligation to avoid deceptive acts
Obligation to perform services within area of competence
Obligation to provide complete design drawings and specifications
Within Competence
false
Synthesis Literal
description
eventRoleContext
foreseenUnintendedEffects
hasAgent
hasMentalState
intendedOutcome
temporalExtent
temporalMarker
temporalSequence
withinCompetence
TTL
@prefix case85: <http://proethica.org/ontology/case/85#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proeth: <http://proethica.org/ontology/intermediate#> . @prefix proeth-core: <http://proethica.org/ontology/core#> . @prefix proeth-prov: <http://proethica.org/provenance#> . @prefix prov: <http://www.w3.org/ns/prov#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix time: <http://www.w3.org/2006/time#> . @prefix xsd: <http://www.w3.org/2001/XMLSchema#> . case85:Incomplete_Work_Submission a proeth-core:Action, owl:NamedIndividual ; rdfs:label "Incomplete Work Submission" ; proeth-core:initiates case85:Engineer_A_Incomplete_Deliverable ; proeth:conceptCategory "Action" ; proeth:eventRoleContext "Design Engineer" ; proeth:foreseenUnintendedEffects "Risk of increased project costs", "Submission of documents insufficient to support construction" ; proeth:guidedByPrinciple case85:Engineer_A_Deliverable_Completeness_Concealment, case85:Engineer_A_Deliverable_Completeness_Disclosure_Principle, case85:Engineer_A_Honesty_Concealment_of_Deficiency, case85:Engineer_A_Public_Funds_Misrepresentation ; proeth:guidedByPrincipleText "Completeness of professional deliverables", "Honest representation to client", "Public fund stewardship" ; proeth:hasAgent "Engineer A" ; proeth:hasMentalState "deliberate" ; proeth:initiatesText "Incomplete Documents in Circulation", "Public Safety Risk Latent", "Unjustified Expenditure of Public Funds Risk" ; proeth:intendedOutcome "Meet the contractual delivery deadline and avoid conflict with the client over schedule" ; proeth:requiresCapabilityText "Conformance with applicable engineering standards", "Dam design to completion", "Scheduling judgment to flag infeasible deadlines" ; proeth:temporalExtent "instant" ; proeth:temporalMarker "Design phase, at the deadline for deliverable submission" ; proeth:temporalSequence 5 ; proeth:violatesObligation case85:Engineer_A_Competence_Dam_Drawings_Obligation, case85:Engineer_A_Complete_Design_Delivery, case85:Engineer_A_Public_Funds_Misrepresentation_Obligation ; proeth:violatesObligationText "Obligation to avoid deceptive acts", "Obligation to perform services within area of competence", "Obligation to provide complete design drawings and specifications" ; proeth:withinCompetence false ; proeth-prov:synthesisLiteral "description", "eventRoleContext", "foreseenUnintendedEffects", "hasAgent", "hasMentalState", "intendedOutcome", "temporalExtent", "temporalMarker", "temporalSequence", "withinCompetence" ; rdfs:comment "Engineer A decided to submit drawings and specifications that he knew to be incomplete by the specified deadline, citing time pressure as justification, rather than requesting an extension or otherwise seeking relief from the schedule constraint." ; time:hasTime case85:time_Incomplete_Work_Submission ; prov:wasAttributedTo "claude-sonnet-4-6" ; prov:wasGeneratedBy "ProEthica Case 85 Extraction" .
Metadata
Type
Individual
Last Updated
2026-06-05 09:48
Attributed to
claude-sonnet-4-6
Generated by
ProEthica Case 85 Extraction