Engineer A Deliverable Completeness Disclosure

P · Principle Individual
http://proethica.org/ontology/case/85#Engineer_A_Deliverable_Completeness_Disclosure_Principle
Definition

Engineer A submitted incomplete design drawings and specifications for the dam project while asserting that the incompleteness was due to time pressures and an expectation of future federal funding, without disclosing the deficiency to the client or approving authority at the time of submission.

Properties
Instance of
DeliverableCompletenessDisclosurePrinciple
http://proethica.org/ontology/intermediate#DeliverableCompletenessDisclosurePrinciple
Applied to
Dam design drawings and specifications submitted to the local public agency and federal agency
Balancing with
Faithful Agent Duty Principle
Concrete expression
Engineer A submitted incomplete design drawings and specifications for the dam project while asserting that the incompleteness was due to time pressures and an expectation of future federal funding, without disclosing the deficiency to the client or approving authority at the time of submission.
Confidence
0.95
Interpretation
The principle required Engineer A to disclose the known incompleteness of the drawings at the time of submission rather than submitting deficient work while concealing its inadequacy.
Tension resolution
The Board found no legitimate basis for Engineer A's conduct; the obligation to deliver complete work and to disclose incompleteness was not outweighed by time pressures or funding expectations.
Match Confidence
0.0
Matches Existing
false
Synthesis Literal
appliedTo
balancingWith
concreteExpression
confidence
interpretation
principleClass
tensionResolution
textReferences
Relationships
invokedBy Agent Engineer A
Source Evidence
Text references
Engineer A had an obligation to provide a complete set of design drawings and specifications on the project in which Engineer A was engaged
Engineer A's bold assertion that the work was incomplete, but that this was due to time pressures and his expectation that Federal funds would be awarded to complete the work is wholly unconvincing

Source text
Engineer A had an obligation to provide a complete set of design drawings and specifications on the project in which Engineer A was engaged.
TTL
@prefix case85: <http://proethica.org/ontology/case/85#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proeth: <http://proethica.org/ontology/intermediate#> . @prefix proeth-core: <http://proethica.org/ontology/core#> . @prefix proeth-prov: <http://proethica.org/provenance#> . @prefix prov: <http://www.w3.org/ns/prov#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix skos: <http://www.w3.org/2004/02/skos/core#> . @prefix xsd: <http://www.w3.org/2001/XMLSchema#> . case85:Engineer_A_Deliverable_Completeness_Disclosure_Principle a proeth:DeliverableCompletenessDisclosurePrinciple, owl:NamedIndividual ; rdfs:label "Engineer A Deliverable Completeness Disclosure" ; proeth-core:invokedBy case85:Agent_Engineer_A ; proeth:appliedTo "Dam design drawings and specifications submitted to the local public agency and federal agency" ; proeth:balancingWith "Faithful Agent Duty Principle" ; proeth:conceptCategory "Principle" ; proeth:concreteExpression "Engineer A submitted incomplete design drawings and specifications for the dam project while asserting that the incompleteness was due to time pressures and an expectation of future federal funding, without disclosing the deficiency to the client or approving authority at the time of submission." ; proeth:confidence "0.95" ; proeth:interpretation "The principle required Engineer A to disclose the known incompleteness of the drawings at the time of submission rather than submitting deficient work while concealing its inadequacy." ; proeth:invokedBy "Engineer A Dam Design Engineer" ; proeth:principleClass "Deliverable Completeness Disclosure Principle" ; proeth:tensionResolution "The Board found no legitimate basis for Engineer A's conduct; the obligation to deliver complete work and to disclose incompleteness was not outweighed by time pressures or funding expectations." ; proeth:textReferences "Engineer A had an obligation to provide a complete set of design drawings and specifications on the project in which Engineer A was engaged", "Engineer A's bold assertion that the work was incomplete, but that this was due to time pressures and his expectation that Federal funds would be awarded to complete the work is wholly unconvincing" ; proeth-prov:discoveredInCase 85 ; proeth-prov:discoveredInPass 2 ; proeth-prov:discoveredInSection "discussion" ; proeth-prov:firstDiscoveredAt "2026-06-04T16:53:07.457315+00:00"^^xsd:dateTime ; proeth-prov:firstDiscoveredInCase 85 ; proeth-prov:matchConfidence 0.0 ; proeth-prov:matchesExisting false ; proeth-prov:sourceText "Engineer A had an obligation to provide a complete set of design drawings and specifications on the project in which Engineer A was engaged." ; proeth-prov:synthesisLiteral "appliedTo", "balancingWith", "concreteExpression", "confidence", "interpretation", "principleClass", "tensionResolution", "textReferences" ; rdfs:comment "Engineer A submitted incomplete design drawings and specifications for the dam project while asserting that the incompleteness was due to time pressures and an expectation of future federal funding, without disclosing the deficiency to the client or approving authority at the time of submission." ; skos:definition "Engineer A submitted incomplete design drawings and specifications for the dam project while asserting that the incompleteness was due to time pressures and an expectation of future federal funding, without disclosing the deficiency to the client or approving authority at the time of submission." ; prov:generatedAtTime "2026-06-04T16:53:07.457315+00:00"^^xsd:dateTime ; prov:wasAttributedTo "Case 85 Extraction", "claude-sonnet-4-6" ; prov:wasGeneratedBy "ProEthica Case 85 Extraction" .
Metadata
Type
Individual
Last Updated
2026-06-05 09:48
Discovered in case
85
Discovered in pass
2
Discovered in section
discussion
First discovered
2026-06-04T16:53:07.457315+00:00
First case
85
Generated
2026-06-04T16:53:07.457315+00:00
Attributed to
['Case 85 Extraction', 'claude-sonnet-4-6']
Generated by
ProEthica Case 85 Extraction