Engineer A Complete Design Delivery

O · Obligation Individual
http://proethica.org/ontology/case/85#Engineer_A_Complete_Design_Delivery
Definition

Engineer A was obligated to provide a complete and buildable set of design drawings and specifications for the dam project, conforming to applicable engineering standards, and was not permitted to submit incomplete documents under seal on the basis of time pressure or anticipated federal funding.

Properties
Instance of
CompleteDesignDeliveryObligation
http://proethica.org/ontology/intermediate#CompleteDesignDeliveryObligation
Case context
Engineer A was retained to produce full design drawings and specifications for a dam project funded in part by federal grants. Engineer A submitted incomplete and partially unbuildable documents under seal, asserting that time pressures and expected federal funds justified the incompleteness.
Compliance status
unmet
Confidence
0.92
Obligation statement
Engineer A was obligated to provide a complete and buildable set of design drawings and specifications for the dam project, conforming to applicable engineering standards, and was not permitted to submit incomplete documents under seal on the basis of time pressure or anticipated federal funding.
Temporal scope
At the time of submission of design documents
Match Confidence
0.0
Matches Existing
false
Synthesis Literal
caseContext
complianceStatus
confidence
obligationClass
obligationStatement
temporalScope
textReferences
Source Evidence
Text references
Engineer A was fully required to provide the complete design on the project.
Engineer A's bold assertion that the work was incomplete, but that this was due to time pressures and his expectation that Federal funds would be awarded to complete the work is wholly unconvincing.
It is clear that Engineer A had an obligation to provide a complete set of design drawings and specifications on the project in which Engineer A was engaged.

Source text
It is clear that Engineer A had an obligation to provide a complete set of design drawings and specifications on the project in which Engineer A was engaged.
TTL
@prefix case85: <http://proethica.org/ontology/case/85#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proeth: <http://proethica.org/ontology/intermediate#> . @prefix proeth-core: <http://proethica.org/ontology/core#> . @prefix proeth-prov: <http://proethica.org/provenance#> . @prefix prov: <http://www.w3.org/ns/prov#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix skos: <http://www.w3.org/2004/02/skos/core#> . @prefix xsd: <http://www.w3.org/2001/XMLSchema#> . case85:Engineer_A_Complete_Design_Delivery a proeth:CompleteDesignDeliveryObligation, owl:NamedIndividual ; rdfs:label "Engineer A Complete Design Delivery" ; proeth-core:competesWith case85:Engineer_A_Deadline_Pressure_Resistance_Obligation ; proeth-core:obligatedParty case85:Agent_Engineer_A ; proeth-core:prevailsOver case85:Engineer_A_Cost_Allocation_Neutrality ; proeth:caseContext "Engineer A was retained to produce full design drawings and specifications for a dam project funded in part by federal grants. Engineer A submitted incomplete and partially unbuildable documents under seal, asserting that time pressures and expected federal funds justified the incompleteness." ; proeth:complianceStatus "unmet" ; proeth:conceptCategory "Obligation" ; proeth:confidence "0.92" ; proeth:derivedFromPrinciple case85:Engineer_A_Deliverable_Completeness_Disclosure_Principle ; proeth:obligatedParty "Engineer A" ; proeth:obligationClass "Complete Design Delivery Obligation" ; proeth:obligationStatement "Engineer A was obligated to provide a complete and buildable set of design drawings and specifications for the dam project, conforming to applicable engineering standards, and was not permitted to submit incomplete documents under seal on the basis of time pressure or anticipated federal funding." ; proeth:temporalScope "At the time of submission of design documents" ; proeth:textReferences "Engineer A was fully required to provide the complete design on the project.", "Engineer A's bold assertion that the work was incomplete, but that this was due to time pressures and his expectation that Federal funds would be awarded to complete the work is wholly unconvincing.", "It is clear that Engineer A had an obligation to provide a complete set of design drawings and specifications on the project in which Engineer A was engaged." ; proeth-prov:discoveredInCase 85 ; proeth-prov:discoveredInPass 2 ; proeth-prov:discoveredInSection "discussion" ; proeth-prov:firstDiscoveredAt "2026-06-04T16:54:40.172403+00:00"^^xsd:dateTime ; proeth-prov:firstDiscoveredInCase 85 ; proeth-prov:matchConfidence 0.0 ; proeth-prov:matchesExisting false ; proeth-prov:sourceText "It is clear that Engineer A had an obligation to provide a complete set of design drawings and specifications on the project in which Engineer A was engaged." ; proeth-prov:synthesisLiteral "caseContext", "complianceStatus", "confidence", "obligationClass", "obligationStatement", "temporalScope", "textReferences" ; rdfs:comment "Engineer A was obligated to provide a complete and buildable set of design drawings and specifications for the dam project, conforming to applicable engineering standards, and was not permitted to submit incomplete documents under seal on the basis of time pressure or anticipated federal funding." ; skos:definition "Engineer A was obligated to provide a complete and buildable set of design drawings and specifications for the dam project, conforming to applicable engineering standards, and was not permitted to submit incomplete documents under seal on the basis of time pressure or anticipated federal funding." ; prov:generatedAtTime "2026-06-04T16:54:40.172403+00:00"^^xsd:dateTime ; prov:wasAttributedTo "Case 85 Extraction", "claude-sonnet-4-6" ; prov:wasGeneratedBy "ProEthica Case 85 Extraction" .
Metadata
Type
Individual
Last Updated
2026-06-05 09:48
Discovered in case
85
Discovered in pass
2
Discovered in section
discussion
First discovered
2026-06-04T16:54:40.172403+00:00
First case
85
Generated
2026-06-04T16:54:40.172403+00:00
Attributed to
['Case 85 Extraction', 'claude-sonnet-4-6']
Generated by
ProEthica Case 85 Extraction