Engineer D's agency issued bid documents for major building renovation projects that made no reference to existing as-built drawings for the existing sprinkler systems, despite those drawings being material to accurate bid preparation and safe execution of fire suppression system renovation work.
Compliance status
unmet
Confidence
0.95
Importance
high
Obligated party
Engineer D
Obligation statement
Engineer D was obligated to identify the existing as-built drawings for sprinkler systems as material to accurate bid preparation and safe performance of renovation work, and to reference and make available those drawings in the bid package for each renovation project.
Temporal scope
During preparation of bid documents for each renovation project involving existing sprinkler systems
Relationships
Source Evidence
Source text
The agency advertises for bids on major building renovation projects; the bid documents made no reference to existing as-builts or drawings for the bidders' or awarded contractor's use.
Text references
Engineer D is a fire protection engineer in the public sector and works for a state agency.
The agency advertises for bids on major building renovation projects; the bid documents made no reference to existing as-builts or drawings for the bidders' or awarded contractor's use.
TTL
@prefix case22: <http://proethica.org/ontology/case/22#> .
@prefix owl: <http://www.w3.org/2002/07/owl#> .
@prefix proeth: <http://proethica.org/ontology/intermediate#> .
@prefix proeth-core: <http://proethica.org/ontology/core#> .
@prefix prov: <http://www.w3.org/ns/prov#> .
@prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> .
@prefix xsd: <http://www.w3.org/2001/XMLSchema#> .
case22:Bid_Document_Material_Information_Inclusion_Engineer_D_Sprinkler_As-Builts a proeth:BidDocumentMaterialInformationInclusionObligation,
owl:NamedIndividual ;
rdfs:label "Bid Document Material Information Inclusion Engineer D Sprinkler As-Builts" ;
proeth-core:prevailsOver case22:Engineer_D_Employer_Information_Consent_Requirement_As-Built_Drawings ;
proeth:casecontext "Engineer D's agency issued bid documents for major building renovation projects that made no reference to existing as-built drawings for the existing sprinkler systems, despite those drawings being material to accurate bid preparation and safe execution of fire suppression system renovation work." ;
proeth:compliancestatus "unmet" ;
proeth:conceptCategory "Obligation" ;
proeth:confidence "0.95" ;
proeth:derivedFromPrinciple case22:Bid_Document_Completeness_Invoked_By_Engineer_D_Omission,
case22:Bid_Document_Completeness_Invoked_for_As-Built_Drawing_Inclusion ;
proeth:discoveredincase "22" ;
proeth:discoveredinpass "2" ;
proeth:discoveredinsection "facts" ;
proeth:firstdiscoveredat "2026-02-25T19:56:04.852603+00:00" ;
proeth:firstdiscoveredincase "22" ;
proeth:generatedattime "2026-02-25T19:56:04.852603+00:00" ;
proeth:importance "high" ;
proeth:obligatedparty "Engineer D" ;
proeth:obligationclass "Bid Document Material Information Inclusion Obligation" ;
proeth:obligationstatement "Engineer D was obligated to identify the existing as-built drawings for sprinkler systems as material to accurate bid preparation and safe performance of renovation work, and to reference and make available those drawings in the bid package for each renovation project." ;
proeth:sourcetext "The agency advertises for bids on major building renovation projects; the bid documents made no reference to existing as-builts or drawings for the bidders' or awarded contractor's use." ;
proeth:temporalscope "During preparation of bid documents for each renovation project involving existing sprinkler systems" ;
proeth:textreferences "Engineer D is a fire protection engineer in the public sector and works for a state agency.",
"The agency advertises for bids on major building renovation projects; the bid documents made no reference to existing as-builts or drawings for the bidders' or awarded contractor's use." ;
proeth:wasattributedto "Case 22 Extraction" ;
prov:generatedAtTime "2026-02-25T20:07:58.296391"^^xsd:dateTime ;
prov:wasGeneratedBy "ProEthica Case 22 Extraction" .
Metadata
Extraction details
Discovered in case
22
Discovered in pass
2
Discovered in section
facts
First discovered
2026-02-25T19:56:04.852603+00:00
First case
22
Generated
2026-02-25T19:56:04.852603+00:00
Attributed to
Case 22 Extraction
Generated
2026-02-25T20:07:58.296391
Generated by
ProEthica Case 22 Extraction