Engineer A was obligated to disclose to the local public agency client, the federal approving engineer, and the bidding contractors that the drawings and specifications were materially incomplete and that certain elements were unbuildable, before or at the time of submitting the sealed documents.
Properties
Instance of
DeliverableCompletenessDisclosureObligation
http://proethica.org/ontology/intermediate#DeliverableCompletenessDisclosureObligation
Case context
Engineer A submitted signed and sealed dam drawings and specifications that he knew were incomplete and contained unbuildable elements, without disclosing those deficiencies to any party, citing schedule pressure as justification.
Compliance status
unmet
Confidence
0.92
Obligation statement
Engineer A was obligated to disclose to the local public agency client, the federal approving engineer, and the bidding contractors that the drawings and specifications were materially incomplete and that certain elements were unbuildable, before or at the time of submitting the sealed documents.
Temporal scope
At or before the time of submitting the signed and sealed drawings and specifications
Match Confidence
0.78
Match Reasoning
Via class 'Deliverable Completeness Disclosure Obligation': The concept is a variant of Complete Technical Reporting Obligation and Report Completeness Obligation, but those address omissions within a report rather than the duty to disclose that a deliverable itself is materially incomplete at the time of submission. The present obligation is sufficiently distinct to warrant a separate class focused on the completeness of the deliverable artifact rather than the completeness of findings within a report.
Matched Ontology Label
Complete Technical Reporting Obligation
Matches Existing
true
Synthesis Literal
caseContext
complianceStatus
confidence
obligationClass
obligationStatement
temporalScope
textReferences
Relationships
obligatedParty
Agent Engineer A
prevailsOver
Engineer A Deadline Pressure Resistance Obligation
Source Evidence
Text references
Engineer A generally agrees with Hi-Lo's characterization, but in his defense responds that he felt pressured to deliver the drawings and specifications on a specified date, but did not inform anyone as to their incompleteness
Source text
Engineer A generally agrees with Hi-Lo's characterization, but in his defense responds that he felt pressured to deliver the drawings and specifications on a specified date, but did not inform anyone as to their incompleteness
TTL
@prefix case85: <http://proethica.org/ontology/case/85#> .
@prefix owl: <http://www.w3.org/2002/07/owl#> .
@prefix proeth: <http://proethica.org/ontology/intermediate#> .
@prefix proeth-core: <http://proethica.org/ontology/core#> .
@prefix proeth-prov: <http://proethica.org/provenance#> .
@prefix prov: <http://www.w3.org/ns/prov#> .
@prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> .
@prefix skos: <http://www.w3.org/2004/02/skos/core#> .
@prefix xsd: <http://www.w3.org/2001/XMLSchema#> .
case85:Engineer_A_Deliverable_Completeness_Disclosure a proeth:DeliverableCompletenessDisclosureObligation,
owl:NamedIndividual ;
rdfs:label "Engineer A Deliverable Completeness Disclosure" ;
proeth-core:obligatedParty case85:Agent_Engineer_A ;
proeth-core:prevailsOver case85:Engineer_A_Deadline_Pressure_Resistance_Obligation ;
proeth:caseContext "Engineer A submitted signed and sealed dam drawings and specifications that he knew were incomplete and contained unbuildable elements, without disclosing those deficiencies to any party, citing schedule pressure as justification." ;
proeth:complianceStatus "unmet" ;
proeth:conceptCategory "Obligation" ;
proeth:confidence "0.92" ;
proeth:derivedFromPrinciple case85:Engineer_A_Deliverable_Completeness_Disclosure_Principle,
case85:Engineer_A_Transparency_Deficient_Submission ;
proeth:obligatedParty "Engineer A" ;
proeth:obligationClass "Deliverable Completeness Disclosure Obligation" ;
proeth:obligationStatement "Engineer A was obligated to disclose to the local public agency client, the federal approving engineer, and the bidding contractors that the drawings and specifications were materially incomplete and that certain elements were unbuildable, before or at the time of submitting the sealed documents." ;
proeth:temporalScope "At or before the time of submitting the signed and sealed drawings and specifications" ;
proeth:textReferences "Engineer A generally agrees with Hi-Lo's characterization, but in his defense responds that he felt pressured to deliver the drawings and specifications on a specified date, but did not inform anyone as to their incompleteness" ;
proeth-prov:discoveredInCase 85 ;
proeth-prov:discoveredInPass 2 ;
proeth-prov:discoveredInSection "facts" ;
proeth-prov:firstDiscoveredAt "2026-06-04T16:50:13.568162+00:00"^^xsd:dateTime ;
proeth-prov:firstDiscoveredInCase 85 ;
proeth-prov:matchConfidence 0.78 ;
proeth-prov:matchReasoning "Via class 'Deliverable Completeness Disclosure Obligation': The concept is a variant of Complete Technical Reporting Obligation and Report Completeness Obligation, but those address omissions within a report rather than the duty to disclose that a deliverable itself is materially incomplete at the time of submission. The present obligation is sufficiently distinct to warrant a separate class focused on the completeness of the deliverable artifact rather than the completeness of findings within a report." ;
proeth-prov:matchedOntologyClass proeth:CompleteOptionsAdvisoryObligation ;
proeth-prov:matchedOntologyLabel "Complete Technical Reporting Obligation" ;
proeth-prov:matchesExisting true ;
proeth-prov:sourceText "Engineer A generally agrees with Hi-Lo's characterization, but in his defense responds that he felt pressured to deliver the drawings and specifications on a specified date, but did not inform anyone as to their incompleteness" ;
proeth-prov:synthesisLiteral "caseContext",
"complianceStatus",
"confidence",
"obligationClass",
"obligationStatement",
"temporalScope",
"textReferences" ;
rdfs:comment "Engineer A was obligated to disclose to the local public agency client, the federal approving engineer, and the bidding contractors that the drawings and specifications were materially incomplete and that certain elements were unbuildable, before or at the time of submitting the sealed documents." ;
skos:definition "Engineer A was obligated to disclose to the local public agency client, the federal approving engineer, and the bidding contractors that the drawings and specifications were materially incomplete and that certain elements were unbuildable, before or at the time of submitting the sealed documents." ;
prov:generatedAtTime "2026-06-04T16:50:13.568162+00:00"^^xsd:dateTime ;
prov:wasAttributedTo "Case 85 Extraction",
"claude-sonnet-4-6" ;
prov:wasGeneratedBy "ProEthica Case 85 Extraction" .
Metadata
Extraction details
Discovered in case
85
Discovered in pass
2
Discovered in section
facts
First discovered
2026-06-04T16:50:13.568162+00:00
First case
85
Generated
2026-06-04T16:50:13.568162+00:00
Attributed to
['Case 85 Extraction', 'claude-sonnet-4-6']
Generated by
ProEthica Case 85 Extraction