Engineer A Complete Options Advisory

O · Obligation Individual
http://proethica.org/ontology/case/14#Engineer_A_Complete_Options_Advisory
Definition

Engineer A was obligated to present all four funding-agency-approved project delivery methods to City B in the advisory memo, rather than limiting the analysis to Design-Bid-Build and Progressive-Design-Build.

Properties
Instance of
CompleteOptionsAdvisoryObligation
http://proethica.org/ontology/intermediate#CompleteOptionsAdvisoryObligation
Case context
Engineer A prepared a summary memo for City B Administrator advising on project delivery methods for a wastewater system improvements project funded by a specific funding source that approved four delivery methods. Engineer A omitted Construction-Manager-at-Risk and Fixed-Price-Design-Build from the memo.
Compliance status
unmet
Confidence
0.93
Obligation statement
Engineer A was obligated to present all four funding-agency-approved project delivery methods to City B in the advisory memo, rather than limiting the analysis to Design-Bid-Build and Progressive-Design-Build.
Temporal scope
At the time of preparing and submitting the advisory memo to City B Administrator
Match Confidence
0.0
Matches Existing
false
Synthesis Literal
caseContext
complianceStatus
confidence
obligationClass
obligationStatement
temporalScope
textReferences
Relationships
obligatedParty Agent Engineer A
Source Evidence
Text references
Engineer A prepared a summary memo to City B Administrator and only identified Design-Bid-Build and Progressive-Design-Build as viable project delivery options.
Under the proposed funding source, there are four approved project delivery methods: Design-Bid-Build, Construction-Management-at-Risk, Fixed-Price-Design-Build, and Progressive-Design-Build.

Source text
Under the proposed funding source, there are four approved project delivery methods: Design-Bid-Build, Construction-Management-at-Risk, Fixed-Price-Design-Build, and Progressive-Design-Build.
TTL
@prefix case14: <http://proethica.org/ontology/case/14#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proeth: <http://proethica.org/ontology/intermediate#> . @prefix proeth-core: <http://proethica.org/ontology/core#> . @prefix proeth-prov: <http://proethica.org/provenance#> . @prefix prov: <http://www.w3.org/ns/prov#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix skos: <http://www.w3.org/2004/02/skos/core#> . @prefix xsd: <http://www.w3.org/2001/XMLSchema#> . case14:Engineer_A_Complete_Options_Advisory a proeth:CompleteOptionsAdvisoryObligation, owl:NamedIndividual ; rdfs:label "Engineer A Complete Options Advisory" ; proeth-core:defeasibleUnder case14:Engineer_A_Selective_Option_Disclosure ; proeth-core:obligatedParty case14:Agent_Engineer_A ; proeth:caseContext "Engineer A prepared a summary memo for City B Administrator advising on project delivery methods for a wastewater system improvements project funded by a specific funding source that approved four delivery methods. Engineer A omitted Construction-Manager-at-Risk and Fixed-Price-Design-Build from the memo." ; proeth:complianceStatus "unmet" ; proeth:conceptCategory "Obligation" ; proeth:confidence "0.93" ; proeth:derivedFromPrinciple case14:Engineer_A_Complete_Options_Analysis ; proeth:obligatedParty "Engineer A" ; proeth:obligationClass "Complete Options Advisory Obligation" ; proeth:obligationStatement "Engineer A was obligated to present all four funding-agency-approved project delivery methods to City B in the advisory memo, rather than limiting the analysis to Design-Bid-Build and Progressive-Design-Build." ; proeth:temporalScope "At the time of preparing and submitting the advisory memo to City B Administrator" ; proeth:textReferences "Engineer A prepared a summary memo to City B Administrator and only identified Design-Bid-Build and Progressive-Design-Build as viable project delivery options.", "Under the proposed funding source, there are four approved project delivery methods: Design-Bid-Build, Construction-Management-at-Risk, Fixed-Price-Design-Build, and Progressive-Design-Build." ; proeth-prov:discoveredInCase 14 ; proeth-prov:discoveredInPass 2 ; proeth-prov:discoveredInSection "facts" ; proeth-prov:firstDiscoveredAt "2026-06-04T08:44:38.157284+00:00"^^xsd:dateTime ; proeth-prov:firstDiscoveredInCase 14 ; proeth-prov:matchConfidence 0.0 ; proeth-prov:matchesExisting false ; proeth-prov:sourceText "Under the proposed funding source, there are four approved project delivery methods: Design-Bid-Build, Construction-Management-at-Risk, Fixed-Price-Design-Build, and Progressive-Design-Build." ; proeth-prov:synthesisLiteral "caseContext", "complianceStatus", "confidence", "obligationClass", "obligationStatement", "temporalScope", "textReferences" ; rdfs:comment "Engineer A was obligated to present all four funding-agency-approved project delivery methods to City B in the advisory memo, rather than limiting the analysis to Design-Bid-Build and Progressive-Design-Build." ; skos:definition "Engineer A was obligated to present all four funding-agency-approved project delivery methods to City B in the advisory memo, rather than limiting the analysis to Design-Bid-Build and Progressive-Design-Build." ; prov:generatedAtTime "2026-06-04T08:44:38.157284+00:00"^^xsd:dateTime ; prov:wasAttributedTo "Case 14 Extraction", "claude-sonnet-4-6" ; prov:wasGeneratedBy "ProEthica Case 14 Extraction" .
Metadata
Type
Individual
Last Updated
2026-06-05 09:40
Discovered in case
14
Discovered in pass
2
Discovered in section
facts
First discovered
2026-06-04T08:44:38.157284+00:00
First case
14
Generated
2026-06-04T08:44:38.157284+00:00
Attributed to
['Case 14 Extraction', 'claude-sonnet-4-6']
Generated by
ProEthica Case 14 Extraction