Engineer A Sanitary System Overflow Proactive Capacity Warning to Administrator C

O · Obligation Individual
http://proethica.org/ontology/case/92#Engineer_A_Sanitary_System_Overflow_Proactive_Capacity_Warning_to_Administrator_C
Properties
Instance of
SanitarySystemOverflowProactiveCapacityWarningObligation
http://proethica.org/ontology/intermediate#SanitarySystemOverflowProactiveCapacityWarningObligation
Case context
Engineer A identified that the city's sanitary system lacked capacity to handle the combined load of industrial vegetable waste discharge during canning season and stormwater during the rainy season, and notified Administrator C with proposed solutions.
Compliance status
met
Confidence
0.92
Importance
high
Obligated party
Engineer A (City Engineer/Director of Public Works)
Obligation statement
Engineer A was obligated to proactively notify Administrator C of the inadequate capacity of the disposal plant and beds to handle potential overflow during the rainy/canning season and to offer possible solutions.
Temporal scope
During the course of employment, prior to the canning/rainy season crisis
Source Evidence
Source text
Engineer A notifies Administrator C of the inadequate capacity of the plant and beds to handle the potential overflow during the rainy season and offers possible solutions.

Text references
Engineer A notifies Administrator C of the inadequate capacity of the plant and beds to handle the potential overflow during the rainy season and offers possible solutions.
TTL
@prefix case92: <http://proethica.org/ontology/case/92#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proeth: <http://proethica.org/ontology/intermediate#> . @prefix prov: <http://www.w3.org/ns/prov#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix xsd: <http://www.w3.org/2001/XMLSchema#> . case92:Engineer_A_Sanitary_System_Overflow_Proactive_Capacity_Warning_to_Administrator_C a proeth:SanitarySystemOverflowProactiveCapacityWarningObligation, owl:NamedIndividual ; rdfs:label "Engineer A Sanitary System Overflow Proactive Capacity Warning to Administrator C" ; proeth:casecontext "Engineer A identified that the city's sanitary system lacked capacity to handle the combined load of industrial vegetable waste discharge during canning season and stormwater during the rainy season, and notified Administrator C with proposed solutions." ; proeth:compliancestatus "met" ; proeth:conceptCategory "Obligation" ; proeth:confidence "0.92" ; proeth:derivedFromPrinciple case92:Proactive_Risk_Disclosure_Invoked_by_Engineer_A_for_Overflow_Warning ; proeth:discoveredincase "92" ; proeth:discoveredinpass "2" ; proeth:discoveredinsection "facts" ; proeth:firstdiscoveredat "2026-03-01T13:39:18.625356+00:00" ; proeth:firstdiscoveredincase "92" ; proeth:generatedattime "2026-03-01T13:39:18.625356+00:00" ; proeth:importance "high" ; proeth:obligatedparty "Engineer A (City Engineer/Director of Public Works)" ; proeth:obligationclass "Sanitary System Overflow Proactive Capacity Warning Obligation" ; proeth:obligationstatement "Engineer A was obligated to proactively notify Administrator C of the inadequate capacity of the disposal plant and beds to handle potential overflow during the rainy/canning season and to offer possible solutions." ; proeth:sourcetext "Engineer A notifies Administrator C of the inadequate capacity of the plant and beds to handle the potential overflow during the rainy season and offers possible solutions." ; proeth:temporalscope "During the course of employment, prior to the canning/rainy season crisis" ; proeth:textreferences "Engineer A notifies Administrator C of the inadequate capacity of the plant and beds to handle the potential overflow during the rainy season and offers possible solutions." ; proeth:wasattributedto "Case 92 Extraction" ; prov:generatedAtTime "2026-03-01T14:00:16.246433"^^xsd:dateTime ; prov:wasGeneratedBy "ProEthica Case 92 Extraction" .
Metadata
Type
Individual
Last Updated
2026-05-28 16:26
Discovered in case
92
Discovered in pass
2
Discovered in section
facts
First discovered
2026-03-01T13:39:18.625356+00:00
First case
92
Generated
2026-03-01T13:39:18.625356+00:00
Attributed to
Case 92 Extraction
Generated
2026-03-01T14:00:16.246433
Generated by
ProEthica Case 92 Extraction