Proactive Risk Disclosure Invoked by Engineer A for Overflow Warning

P · Principle Individual
http://proethica.org/ontology/case/92#Proactive_Risk_Disclosure_Invoked_by_Engineer_A_for_Overflow_Warning
Properties
Instance of
ProactiveRiskDisclosure
http://proethica.org/ontology/intermediate#ProactiveRiskDisclosure
Applied to
Proposed solutions for overflow prevention
Sanitary system capacity inadequacy warning to Administrator C
Balancing with
Faithful Agent Obligation Within Ethical Limits
Loyalty
Concrete expression
Engineer A proactively identified and communicated the inadequate capacity of the disposal plant and beds before the canning/rainy season crisis materialized, offering possible solutions — demonstrating the professional obligation to disclose identified risks before harm occurs rather than waiting for the crisis
Confidence
0.93
Importance
high
Interpretation
Proactive risk disclosure required Engineer A to communicate the overflow risk with sufficient specificity and urgency to enable remedial action, and to persist in that communication when initial reports were dismissed
Invoked by
Engineer A City Engineer Sanitary System
Tension resolution
Proactive risk disclosure obligation was not discharged by a single internal report; Engineer A's repeated escalation to multiple authorities reflected proper fulfillment of the proactive disclosure duty
Source Evidence
Source text
Engineer A notifies Administrator C of the inadequate capacity of the plant and beds to handle the potential overflow during the rainy season and offers possible solutions.

Text references
City Administrator C has told Engineer A that 'we will face the problem when it comes.'
Engineer A notifies Administrator C of the inadequate capacity of the plant and beds to handle the potential overflow during the rainy season and offers possible solutions.
TTL
@prefix case92: <http://proethica.org/ontology/case/92#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proeth: <http://proethica.org/ontology/intermediate#> . @prefix prov: <http://www.w3.org/ns/prov#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix xsd: <http://www.w3.org/2001/XMLSchema#> . case92:Proactive_Risk_Disclosure_Invoked_by_Engineer_A_for_Overflow_Warning a proeth:ProactiveRiskDisclosure, owl:NamedIndividual ; rdfs:label "Proactive Risk Disclosure Invoked by Engineer A for Overflow Warning" ; proeth:appliedto "Proposed solutions for overflow prevention", "Sanitary system capacity inadequacy warning to Administrator C" ; proeth:balancingwith "Faithful Agent Obligation Within Ethical Limits", "Loyalty" ; proeth:conceptCategory "Principle" ; proeth:concreteexpression "Engineer A proactively identified and communicated the inadequate capacity of the disposal plant and beds before the canning/rainy season crisis materialized, offering possible solutions — demonstrating the professional obligation to disclose identified risks before harm occurs rather than waiting for the crisis" ; proeth:confidence "0.93" ; proeth:discoveredincase "92" ; proeth:discoveredinpass "2" ; proeth:discoveredinsection "facts" ; proeth:firstdiscoveredat "2026-03-01T13:37:08.179379+00:00" ; proeth:firstdiscoveredincase "92" ; proeth:generatedattime "2026-03-01T13:37:08.179379+00:00" ; proeth:importance "high" ; proeth:interpretation "Proactive risk disclosure required Engineer A to communicate the overflow risk with sufficient specificity and urgency to enable remedial action, and to persist in that communication when initial reports were dismissed" ; proeth:invokedby "Engineer A City Engineer Sanitary System" ; proeth:principleclass "Proactive Risk Disclosure" ; proeth:sourcetext "Engineer A notifies Administrator C of the inadequate capacity of the plant and beds to handle the potential overflow during the rainy season and offers possible solutions." ; proeth:tensionresolution "Proactive risk disclosure obligation was not discharged by a single internal report; Engineer A's repeated escalation to multiple authorities reflected proper fulfillment of the proactive disclosure duty" ; proeth:textreferences "City Administrator C has told Engineer A that 'we will face the problem when it comes.'", "Engineer A notifies Administrator C of the inadequate capacity of the plant and beds to handle the potential overflow during the rainy season and offers possible solutions." ; proeth:wasattributedto "Case 92 Extraction" ; prov:generatedAtTime "2026-03-01T14:00:16.244344"^^xsd:dateTime ; prov:wasGeneratedBy "ProEthica Case 92 Extraction" .
Metadata
Type
Individual
Last Updated
2026-05-28 16:26
Discovered in case
92
Discovered in pass
2
Discovered in section
facts
First discovered
2026-03-01T13:37:08.179379+00:00
First case
92
Generated
2026-03-01T13:37:08.179379+00:00
Attributed to
Case 92 Extraction
Generated
2026-03-01T14:00:16.244344
Generated by
ProEthica Case 92 Extraction