Client Rejection of On-Site Safety Representative on Cost Grounds

S · State Individual
http://proethica.org/ontology/case/89#Client_Rejection_of_On-Site_Safety_Representative_on_Cost_Grounds
Properties
Instance of
ClientCost-DrivenSafetyOversightRejectionState
http://proethica.org/ontology/intermediate#ClientCost-DrivenSafetyOversightRejectionState
Active period
From client's cost-based refusal through Engineer A's decision to proceed without the safeguard
Affected parties
Client
Construction workers
Engineer A
Public
Confidence
0.98
Importance
high
Subject
Client's refusal to fund a full-time on-site project representative recommended by Engineer A
Terminated by
Client reversal of decision, Engineer A disassociation, or project completion
Triggering event
Client indicates the project would be too costly if a full-time on-site representative were hired
Urgency level
high
Source Evidence
Source text
After reviewing the completed project plans and costs, the client indicates to Engineer A that the project would be too costly if such a representative were hired

Text references
After reviewing the completed project plans and costs, the client indicates to Engineer A that the project would be too costly if such a representative were hired
TTL
@prefix case89: <http://proethica.org/ontology/case/89#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proeth: <http://proethica.org/ontology/intermediate#> . @prefix prov: <http://www.w3.org/ns/prov#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix xsd: <http://www.w3.org/2001/XMLSchema#> . case89:Client_Rejection_of_On-Site_Safety_Representative_on_Cost_Grounds a proeth:ClientCost-DrivenSafetyOversightRejectionState, owl:NamedIndividual ; rdfs:label "Client Rejection of On-Site Safety Representative on Cost Grounds" ; proeth:activeperiod "From client's cost-based refusal through Engineer A's decision to proceed without the safeguard" ; proeth:affectedparties "Client", "Construction workers", "Engineer A", "Public" ; proeth:conceptCategory "State" ; proeth:confidence "0.98" ; proeth:discoveredincase "89" ; proeth:discoveredinpass "1" ; proeth:discoveredinsection "facts" ; proeth:firstdiscoveredat "2026-03-01T18:07:12.075933+00:00" ; proeth:firstdiscoveredincase "89" ; proeth:generatedattime "2026-03-01T18:07:12.075933+00:00" ; proeth:importance "high" ; proeth:sourcetext "After reviewing the completed project plans and costs, the client indicates to Engineer A that the project would be too costly if such a representative were hired" ; proeth:stateclass "Client Cost-Driven Safety Oversight Rejection State" ; proeth:subject "Client's refusal to fund a full-time on-site project representative recommended by Engineer A" ; proeth:terminatedby "Client reversal of decision, Engineer A disassociation, or project completion" ; proeth:textreferences "After reviewing the completed project plans and costs, the client indicates to Engineer A that the project would be too costly if such a representative were hired" ; proeth:triggeringevent "Client indicates the project would be too costly if a full-time on-site representative were hired" ; proeth:urgencylevel "high" ; proeth:wasattributedto "Case 89 Extraction" ; prov:generatedAtTime "2026-03-01T18:38:27.064330"^^xsd:dateTime ; prov:wasGeneratedBy "ProEthica Case 89 Extraction" .
Metadata
Type
Individual
Last Updated
2026-05-28 16:26
Discovered in case
89
Discovered in pass
1
Discovered in section
facts
First discovered
2026-03-01T18:07:12.075933+00:00
First case
89
Generated
2026-03-01T18:07:12.075933+00:00
Attributed to
Case 89 Extraction
Generated
2026-03-01T18:38:27.064330
Generated by
ProEthica Case 89 Extraction