Climate-Informed Design Obligation Activation — Tidal Crossing Upgrade
Individual
6cffa868
http://proethica.org/ontology/case/88#Climate-Informed_Design_Obligation_Activation_—_Tidal_Crossing_Upgrade
Properties
Parent
Climate-InformedDesignObligationActivationState
http://proethica.org/ontology/intermediate#Climate-InformedDesignObligationActivationState
Activeperiod
From Engineer A's formation of professional judgment through resolution (analysis conducted, client informed, or Engineer A withdraws)
Affectedparties
Client B
Engineer A
Regulatory authorities
Upstream homeowners
Concept Category
State
Confidence
0.96
Importance
high
Stateclass
Climate-Informed Design Obligation Activation State
Subject
Engineer A's professional judgment regarding the inadequacy of regulatory requirements for the tidal crossing project
Terminatedby
Client B authorizing the specialized analysis, Engineer A disclosing risks to regulatory authorities, or Engineer A withdrawing from the project
Triggeringevent
Engineer A's determination, based on conference-presented hydraulic evaluation procedures, that regulatory compliance alone is insufficient to protect upstream homeowners under projected climate conditions
Urgencylevel
high
Source Evidence
Source Text
It is Engineer A's judgment, based on hydraulic evaluation procedures presented at a recent transportation agency conference, that the proposed project may result in some upstream homes becoming uninhabitable a decade or more earlier than would otherwise be the case.
Text References
Engineer A proposes a complex and costly hydrologic and hydraulic analysis by a specialized subconsultant to predict the extent to which sea level rise and the increased hydraulic capacity of the tidal crossing will result in flood damage to a neighborhood of twenty upstream homes during future high tides and storm surges, anticipating this to be a difficult question to answer in the project's public hearings.
It is Engineer A's judgment, based on hydraulic evaluation procedures presented at a recent transportation agency conference, that the proposed project may result in some upstream homes becoming uninhabitable a decade or more earlier than would otherwise be the case.
TTL
@prefix rdf: <http://www.w3.org/1999/02/22-rdf-syntax-ns#> .
@prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> .
@prefix owl: <http://www.w3.org/2002/07/owl#> .
@prefix proethica_case_88: <http://proethica.org/ontology/case/88> .
<http://proethica.org/ontology/case/88#Climate-Informed_Design_Obligation_Activation_—_Tidal_Crossing_Upgrade> a owl:NamedIndividual ;
rdfs:label "Climate-Informed Design Obligation Activation — Tidal Crossing Upgrade" ;
rdfs:subClassOf <http://proethica.org/ontology/intermediate#Climate-InformedDesignObligationActivationState> .
Metadata
Ontology
Type
Individual
Content Hash
6cffa868380cb342...Last Updated
2026-03-08 16:29
Extraction Provenance
Discovered in Case
88
Discovered in Pass
1
Discovered in Section
facts
First Discovered
2026-02-27T06:39:47.280651+00:00
First Case
88
Generated
2026-02-27T06:39:47.280651+00:00
Attributed To
Case 88 Extraction
Generated
2026-02-28T10:32:26.860692
Generated By
ProEthica Case 88 Extraction