Engineer A was required to disclose to the local public agency, the federal approving engineer, and bidding contractors that the submitted drawings and specifications were materially incomplete before or at the time of submission.
Properties
Instance of
IncompleteDeliverableDisclosureConstraint
http://proethica.org/ontology/intermediate#IncompleteDeliverableDisclosureConstraint
Case context
Engineer A submitted incomplete dam design documents without disclosing their incompleteness to the client, the federal approving authority, or contractors who would rely on them for bidding.
Confidence
0.9
Constraint statement
Engineer A was required to disclose to the local public agency, the federal approving engineer, and bidding contractors that the submitted drawings and specifications were materially incomplete before or at the time of submission.
Severity
critical
Source
NSPE Code of Ethics
Temporal scope
At the time of submission of incomplete drawings and specifications
Match Confidence
0.0
Matches Existing
false
Synthesis Literal
caseContext
confidence
constraintClass
constraintStatement
severity
source
temporalScope
textReferences
Relationships
constrainedEntity
Agent Engineer A
Source Evidence
Text references
Engineer A had an obligation to provide a complete set of design drawings and specifications on the project
Engineer A's bold assertion that the work was incomplete, but that this was due to time pressures and his expectation that Federal funds would be awarded to complete the work is wholly unconvincing
Source text
Engineer A had an obligation to provide a complete set of design drawings and specifications on the project
TTL
@prefix case85: <http://proethica.org/ontology/case/85#> .
@prefix owl: <http://www.w3.org/2002/07/owl#> .
@prefix proeth: <http://proethica.org/ontology/intermediate#> .
@prefix proeth-core: <http://proethica.org/ontology/core#> .
@prefix proeth-prov: <http://proethica.org/provenance#> .
@prefix prov: <http://www.w3.org/ns/prov#> .
@prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> .
@prefix skos: <http://www.w3.org/2004/02/skos/core#> .
@prefix xsd: <http://www.w3.org/2001/XMLSchema#> .
case85:Engineer_A_Incomplete_Submission_Disclosure a proeth:IncompleteDeliverableDisclosureConstraint,
owl:NamedIndividual ;
rdfs:label "Engineer A Incomplete Submission Disclosure" ;
proeth-core:constrainedEntity case85:Agent_Engineer_A ;
proeth:caseContext "Engineer A submitted incomplete dam design documents without disclosing their incompleteness to the client, the federal approving authority, or contractors who would rely on them for bidding." ;
proeth:conceptCategory "Constraint" ;
proeth:confidence "0.9" ;
proeth:constrainedEntity "Engineer A" ;
proeth:constraintClass "Incomplete Deliverable Disclosure Constraint" ;
proeth:constraintStatement "Engineer A was required to disclose to the local public agency, the federal approving engineer, and bidding contractors that the submitted drawings and specifications were materially incomplete before or at the time of submission." ;
proeth:severity "critical" ;
proeth:source "NSPE Code of Ethics" ;
proeth:temporalScope "At the time of submission of incomplete drawings and specifications" ;
proeth:textReferences "Engineer A had an obligation to provide a complete set of design drawings and specifications on the project",
"Engineer A's bold assertion that the work was incomplete, but that this was due to time pressures and his expectation that Federal funds would be awarded to complete the work is wholly unconvincing" ;
proeth-prov:discoveredInCase 85 ;
proeth-prov:discoveredInPass 2 ;
proeth-prov:discoveredInSection "discussion" ;
proeth-prov:firstDiscoveredAt "2026-06-04T16:56:15.795068+00:00"^^xsd:dateTime ;
proeth-prov:firstDiscoveredInCase 85 ;
proeth-prov:matchConfidence 0.0 ;
proeth-prov:matchesExisting false ;
proeth-prov:sourceText "Engineer A had an obligation to provide a complete set of design drawings and specifications on the project" ;
proeth-prov:synthesisLiteral "caseContext",
"confidence",
"constraintClass",
"constraintStatement",
"severity",
"source",
"temporalScope",
"textReferences" ;
rdfs:comment "Engineer A was required to disclose to the local public agency, the federal approving engineer, and bidding contractors that the submitted drawings and specifications were materially incomplete before or at the time of submission." ;
skos:definition "Engineer A was required to disclose to the local public agency, the federal approving engineer, and bidding contractors that the submitted drawings and specifications were materially incomplete before or at the time of submission." ;
prov:generatedAtTime "2026-06-04T16:56:15.795068+00:00"^^xsd:dateTime ;
prov:wasAttributedTo "Case 85 Extraction",
"claude-sonnet-4-6" ;
prov:wasGeneratedBy "ProEthica Case 85 Extraction" .
Metadata
Extraction details
Discovered in case
85
Discovered in pass
2
Discovered in section
discussion
First discovered
2026-06-04T16:56:15.795068+00:00
First case
85
Generated
2026-06-04T16:56:15.795068+00:00
Attributed to
['Case 85 Extraction', 'claude-sonnet-4-6']
Generated by
ProEthica Case 85 Extraction