DP6

Individual 7fb970bb
http://proethica.org/ontology/case/8#DP6
Properties
Parent
DecisionPoint
http://proethica.org/ontology/cases#DecisionPoint
Decision Point Id
DP6
Decision Question
When Engineer L discloses the confirmed stormwater runoff risk to Client X after resuming work, should Engineer L also disclose the pre-suspension history of the preliminary concern — including that the concern existed before the suspension and before the historic rainfall event — so that Client X can make a fully informed decision about the risk's origins and trajectory?
Focus
Engineer L's obligation to report objectively and completely on the stormwater runoff risk findings — including the developmental history of the concern — and whether post-resumption disclosure that omits the pre-suspension history of concern constitutes a misleading material omission under the Code.
Option1
Disclose the confirmed stormwater risk to Client X together with the pre-suspension history of the preliminary concern, including that the concern predated the historic rainfall event and that it informed the decision to conduct additional studies upon resumption
Option2
Disclose only the currently confirmed stormwater risk findings to Client X without reference to the pre-suspension preliminary concern, treating the earlier concern as a sub-threshold professional intuition that does not require retrospective disclosure
Role Label
Engineer L Public Responsibility
TTL
@prefix rdf: <http://www.w3.org/1999/02/22-rdf-syntax-ns#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proethica_case_8: <http://proethica.org/ontology/case/8> . <http://proethica.org/ontology/case/8#DP6> a owl:NamedIndividual ; rdfs:label "DP6" ; rdfs:subClassOf <http://proethica.org/ontology/cases#DecisionPoint> .
Metadata
Type
Individual
Content Hash
7fb970bb78ed83a9...
Last Updated
2026-03-08 16:29
Extraction Provenance
Generated
2026-02-24T02:55:02.901880
Generated By
ProEthica Case 8 Extraction