Faithful Agent Notification Obligation Invoked by Engineer A for Grid Risk
P · Principle
Individual
http://proethica.org/ontology/case/73#Faithful_Agent_Notification_Obligation_Invoked_by_Engineer_A_for_Grid_Risk
Properties
Instance of
FaithfulAgentNotificationObligationforProjectSuccessRisk
http://proethica.org/ontology/intermediate#FaithfulAgentNotificationObligationforProjectSuccessRisk
Applied to
Organizational Board Decision Authority
Solar energy replacement project viability
Balancing with
Public Welfare Paramount
Trustee Discretion and Deference Obligation
Concrete expression
Engineer A's faithful agent obligation to the organization requires written notification in the board report of the identified risk that the solar-without-storage option may contribute to rolling blackouts during extreme weather events — a risk that threatens the project's functional success (reliable energy supply) even though it arises from conditions outside the organization's direct control (grid-level stress).
Confidence
0.91
Importance
high
Interpretation
The faithful agent relationship encompasses the client's overall project welfare; the rolling blackout risk is a foreseeable threat to the project's ability to reliably serve the organization's energy needs, and the agent must advise the principal of this risk.
Invoked by
Engineer A
Tension resolution
Faithful agent notification and public welfare disclosure converge here: both require Engineer A to include the grid risk in the report, with no tension between them.
Source Evidence
Source text
Engineer A learns that the utility resource planners reviewed their current generation mix and believe that during extreme weather events, they may be forced to institute rolling outages to keep system generating facilities on-line.
Text references
Engineer A also realizes that a move to solar production without storage may stress the local utility generation mix even more, increasing the likelihood of rolling blackouts.
Engineer A learns that the utility resource planners reviewed their current generation mix and believe that during extreme weather events, they may be forced to institute rolling outages to keep system generating facilities on-line.
TTL
@prefix case73: <http://proethica.org/ontology/case/73#> .
@prefix owl: <http://www.w3.org/2002/07/owl#> .
@prefix proeth: <http://proethica.org/ontology/intermediate#> .
@prefix prov: <http://www.w3.org/ns/prov#> .
@prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> .
@prefix xsd: <http://www.w3.org/2001/XMLSchema#> .
case73:Faithful_Agent_Notification_Obligation_Invoked_by_Engineer_A_for_Grid_Risk a proeth:FaithfulAgentNotificationObligationforProjectSuccessRisk,
owl:NamedIndividual ;
rdfs:label "Faithful Agent Notification Obligation Invoked by Engineer A for Grid Risk" ;
proeth:appliedto "Organizational Board Decision Authority",
"Solar energy replacement project viability" ;
proeth:balancingwith "Public Welfare Paramount",
"Trustee Discretion and Deference Obligation" ;
proeth:conceptCategory "Principle" ;
proeth:concreteexpression "Engineer A's faithful agent obligation to the organization requires written notification in the board report of the identified risk that the solar-without-storage option may contribute to rolling blackouts during extreme weather events — a risk that threatens the project's functional success (reliable energy supply) even though it arises from conditions outside the organization's direct control (grid-level stress)." ;
proeth:confidence "0.91" ;
proeth:discoveredincase "73" ;
proeth:discoveredinpass "2" ;
proeth:discoveredinsection "facts" ;
proeth:firstdiscoveredat "2026-02-26T22:36:47.519403+00:00" ;
proeth:firstdiscoveredincase "73" ;
proeth:generatedattime "2026-02-26T22:36:47.519403+00:00" ;
proeth:importance "high" ;
proeth:interpretation "The faithful agent relationship encompasses the client's overall project welfare; the rolling blackout risk is a foreseeable threat to the project's ability to reliably serve the organization's energy needs, and the agent must advise the principal of this risk." ;
proeth:invokedby "Engineer A" ;
proeth:principleclass "Faithful Agent Notification Obligation for Project Success Risk" ;
proeth:sourcetext "Engineer A learns that the utility resource planners reviewed their current generation mix and believe that during extreme weather events, they may be forced to institute rolling outages to keep system generating facilities on-line." ;
proeth:tensionresolution "Faithful agent notification and public welfare disclosure converge here: both require Engineer A to include the grid risk in the report, with no tension between them." ;
proeth:textreferences "Engineer A also realizes that a move to solar production without storage may stress the local utility generation mix even more, increasing the likelihood of rolling blackouts.",
"Engineer A learns that the utility resource planners reviewed their current generation mix and believe that during extreme weather events, they may be forced to institute rolling outages to keep system generating facilities on-line." ;
proeth:wasattributedto "Case 73 Extraction" ;
prov:generatedAtTime "2026-02-26T22:54:37.521062"^^xsd:dateTime ;
prov:wasGeneratedBy "ProEthica Case 73 Extraction" .
Metadata
Extraction details
Discovered in case
73
Discovered in pass
2
Discovered in section
facts
First discovered
2026-02-26T22:36:47.519403+00:00
First case
73
Generated
2026-02-26T22:36:47.519403+00:00
Attributed to
Case 73 Extraction
Generated
2026-02-26T22:54:37.521062
Generated by
ProEthica Case 73 Extraction