Engineer B Fact Gathering Diligence

O · Obligation Individual
http://proethica.org/ontology/case/71#Engineer_B_Fact_Gathering_Diligence
Definition

Engineer B was obligated to inquire of the contractor, on-site workers, and Engineer A's on-site representative to gather all available facts about the original pile driving before reaching conclusions about pile adequacy.

Properties
Instance of
InvestigativeCompletenessObligation
http://proethica.org/ontology/intermediate#InvestigativeCompletenessObligation
Case context
Engineer B supervised test pile driving and produced a findings report without consulting Engineer A's on-site representative or inquiring of the contractor or workers who had direct knowledge of the original pile driving.
Compliance status
unmet
Confidence
0.88
Obligation statement
Engineer B was obligated to inquire of the contractor, on-site workers, and Engineer A's on-site representative to gather all available facts about the original pile driving before reaching conclusions about pile adequacy.
Temporal scope
During the investigation and prior to issuing the findings report.
Match Confidence
0.0
Matches Existing
false
Synthesis Literal
caseContext
complianceStatus
confidence
obligationClass
obligationStatement
temporalScope
textReferences
Relationships
obligatedParty Agent Engineer B
Source Evidence
Text references
Engineer B's failure to inquire from the contractor, workers or others on the job is a failure of fact gathering diligence.
It is clear that Engineer B may be criticized for his failure to communicate with Engineer A's on-site representative.

Source text
Engineer B's failure to inquire from the contractor, workers or others on the job is a failure of fact gathering diligence.
TTL
@prefix case71: <http://proethica.org/ontology/case/71#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proeth: <http://proethica.org/ontology/intermediate#> . @prefix proeth-core: <http://proethica.org/ontology/core#> . @prefix proeth-prov: <http://proethica.org/provenance#> . @prefix prov: <http://www.w3.org/ns/prov#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix skos: <http://www.w3.org/2004/02/skos/core#> . @prefix xsd: <http://www.w3.org/2001/XMLSchema#> . case71:Engineer_B_Fact_Gathering_Diligence a proeth:InvestigativeCompletenessObligation, owl:NamedIndividual ; rdfs:label "Engineer B Fact Gathering Diligence" ; proeth-core:obligatedParty case71:Agent_Engineer_B ; proeth:caseContext "Engineer B supervised test pile driving and produced a findings report without consulting Engineer A's on-site representative or inquiring of the contractor or workers who had direct knowledge of the original pile driving." ; proeth:complianceStatus "unmet" ; proeth:conceptCategory "Obligation" ; proeth:confidence "0.88" ; proeth:derivedFromPrinciple case71:Engineer_B_Investigative_Diligence_Failure ; proeth:obligatedParty "Engineer B" ; proeth:obligationClass "Investigative Completeness Obligation" ; proeth:obligationStatement "Engineer B was obligated to inquire of the contractor, on-site workers, and Engineer A's on-site representative to gather all available facts about the original pile driving before reaching conclusions about pile adequacy." ; proeth:temporalScope "During the investigation and prior to issuing the findings report." ; proeth:textReferences "Engineer B's failure to inquire from the contractor, workers or others on the job is a failure of fact gathering diligence.", "It is clear that Engineer B may be criticized for his failure to communicate with Engineer A's on-site representative." ; proeth-prov:discoveredInCase 71 ; proeth-prov:discoveredInPass 2 ; proeth-prov:discoveredInSection "discussion" ; proeth-prov:firstDiscoveredAt "2026-06-04T14:35:09.835244+00:00"^^xsd:dateTime ; proeth-prov:firstDiscoveredInCase 71 ; proeth-prov:matchConfidence 0.0 ; proeth-prov:matchesExisting false ; proeth-prov:sourceText "Engineer B's failure to inquire from the contractor, workers or others on the job is a failure of fact gathering diligence." ; proeth-prov:synthesisLiteral "caseContext", "complianceStatus", "confidence", "obligationClass", "obligationStatement", "temporalScope", "textReferences" ; rdfs:comment "Engineer B was obligated to inquire of the contractor, on-site workers, and Engineer A's on-site representative to gather all available facts about the original pile driving before reaching conclusions about pile adequacy." ; skos:definition "Engineer B was obligated to inquire of the contractor, on-site workers, and Engineer A's on-site representative to gather all available facts about the original pile driving before reaching conclusions about pile adequacy." ; prov:generatedAtTime "2026-06-04T14:35:09.835244+00:00"^^xsd:dateTime ; prov:wasAttributedTo "Case 71 Extraction", "claude-sonnet-4-6" ; prov:wasGeneratedBy "ProEthica Case 71 Extraction" .
Metadata
Type
Individual
Last Updated
2026-06-05 09:45
Discovered in case
71
Discovered in pass
2
Discovered in section
discussion
First discovered
2026-06-04T14:35:09.835244+00:00
First case
71
Generated
2026-06-04T14:35:09.835244+00:00
Attributed to
['Case 71 Extraction', 'claude-sonnet-4-6']
Generated by
ProEthica Case 71 Extraction