Engineer B Equipment Failure Non-Disclosure

Cs · Constraint Individual
http://proethica.org/ontology/case/71#Engineer_B_Equipment_Failure_Non-Disclosure
Definition

Engineer B was required to disclose in the test report that dynamic test equipment had failed during the test pile program, as this failure directly affected the validity of the data underlying the report's conclusions.

Properties
Instance of
EquipmentFailureDisclosureConstraint
http://proethica.org/ontology/intermediate#EquipmentFailureDisclosureConstraint
Case context
Dynamic test equipment failed during the test pile driving program supervised by Engineer B. This failure was observed and later testified to by Engineer A's geotechnical consultant, but was not disclosed in Engineer B's report.
Confidence
0.91
Constraint statement
Engineer B was required to disclose in the test report that dynamic test equipment had failed during the test pile program, as this failure directly affected the validity of the data underlying the report's conclusions.
Severity
high
Source
NSPE Code of Ethics, professional engineering standards for technical reporting
Temporal scope
At the time of preparing and issuing the test pile program report
Match Confidence
0.0
Matches Existing
false
Synthesis Literal
caseContext
confidence
constraintClass
constraintStatement
severity
source
temporalScope
textReferences
Relationships
constrainedEntity Agent Engineer B
Source Evidence
Text references
Additionally, Engineer B did not report that the dynamic test equipment had failed.
The geotechnical consultant testified and showed that dynamic test equipment had failed during the test.

Source text
Additionally, Engineer B did not report that the dynamic test equipment had failed.
TTL
@prefix case71: <http://proethica.org/ontology/case/71#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proeth: <http://proethica.org/ontology/intermediate#> . @prefix proeth-core: <http://proethica.org/ontology/core#> . @prefix proeth-prov: <http://proethica.org/provenance#> . @prefix prov: <http://www.w3.org/ns/prov#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix skos: <http://www.w3.org/2004/02/skos/core#> . @prefix xsd: <http://www.w3.org/2001/XMLSchema#> . case71:Engineer_B_Equipment_Failure_Non-Disclosure a proeth:EquipmentFailureDisclosureConstraint, owl:NamedIndividual ; rdfs:label "Engineer B Equipment Failure Non-Disclosure" ; proeth-core:constrainedEntity case71:Agent_Engineer_B ; proeth:caseContext "Dynamic test equipment failed during the test pile driving program supervised by Engineer B. This failure was observed and later testified to by Engineer A's geotechnical consultant, but was not disclosed in Engineer B's report." ; proeth:conceptCategory "Constraint" ; proeth:confidence "0.91" ; proeth:constrainedEntity "Engineer B" ; proeth:constraintClass "Equipment Failure Disclosure Constraint" ; proeth:constraintStatement "Engineer B was required to disclose in the test report that dynamic test equipment had failed during the test pile program, as this failure directly affected the validity of the data underlying the report's conclusions." ; proeth:severity "high" ; proeth:source "NSPE Code of Ethics, professional engineering standards for technical reporting" ; proeth:temporalScope "At the time of preparing and issuing the test pile program report" ; proeth:textReferences "Additionally, Engineer B did not report that the dynamic test equipment had failed.", "The geotechnical consultant testified and showed that dynamic test equipment had failed during the test." ; proeth-prov:discoveredInCase 71 ; proeth-prov:discoveredInPass 2 ; proeth-prov:discoveredInSection "facts" ; proeth-prov:firstDiscoveredAt "2026-06-04T14:32:37.486481+00:00"^^xsd:dateTime ; proeth-prov:firstDiscoveredInCase 71 ; proeth-prov:matchConfidence 0.0 ; proeth-prov:matchesExisting false ; proeth-prov:sourceText "Additionally, Engineer B did not report that the dynamic test equipment had failed." ; proeth-prov:synthesisLiteral "caseContext", "confidence", "constraintClass", "constraintStatement", "severity", "source", "temporalScope", "textReferences" ; rdfs:comment "Engineer B was required to disclose in the test report that dynamic test equipment had failed during the test pile program, as this failure directly affected the validity of the data underlying the report's conclusions." ; skos:definition "Engineer B was required to disclose in the test report that dynamic test equipment had failed during the test pile program, as this failure directly affected the validity of the data underlying the report's conclusions." ; prov:generatedAtTime "2026-06-04T14:32:37.486481+00:00"^^xsd:dateTime ; prov:wasAttributedTo "Case 71 Extraction", "claude-sonnet-4-6" ; prov:wasGeneratedBy "ProEthica Case 71 Extraction" .
Metadata
Type
Individual
Last Updated
2026-06-05 09:45
Discovered in case
71
Discovered in pass
2
Discovered in section
facts
First discovered
2026-06-04T14:32:37.486481+00:00
First case
71
Generated
2026-06-04T14:32:37.486481+00:00
Attributed to
['Case 71 Extraction', 'claude-sonnet-4-6']
Generated by
ProEthica Case 71 Extraction