Company B Engineers Project Failure Notification to Employer
O · Obligation
Individual
http://proethica.org/ontology/case/160#Company_B_Engineers_Project_Failure_Notification_to_Employer
Properties
Instance of
ProjectSuccessFailureRiskEmployerNotificationObligation
http://proethica.org/ontology/intermediate#ProjectSuccessFailureRiskEmployerNotificationObligation
Case context
Company B engineers reviewed plans and specifications from Company A for machinery to be used in a manufacturing process, identified miscalculations and technical deficiencies, and notified their employer of their belief that the project would not be successful as designed.
Compliance status
met
Confidence
0.93
Importance
high
Obligated party
Engineers of Company B
Obligation statement
Company B engineers were obligated to notify their employer that they did not believe the project would be successful as designed by Company A engineers, fulfilling their faithful agent obligation under Section 1(c) of the Code.
Temporal scope
Upon identification of miscalculations and technical deficiencies in Company A's plans and specifications, before proceeding with production
Relationships
derivedFromPrinciple
Faithful Agent Notification Obligation Fulfilled by Company B Engineers
Source Evidence
Source text
The engineers of Company 'B' fulfilled their obligation under Section l(c) of the Code by notifying their employer that they did not believe the project would be successful as designed by the engineers of Company 'A'
Text references
The engineers of Company 'B' fulfilled their obligation under Section l(c) of the Code by notifying their employer that they did not believe the project would be successful as designed by the engineers of Company 'A'
TTL
@prefix case160: <http://proethica.org/ontology/case/160#> .
@prefix owl: <http://www.w3.org/2002/07/owl#> .
@prefix proeth: <http://proethica.org/ontology/intermediate#> .
@prefix prov: <http://www.w3.org/ns/prov#> .
@prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> .
@prefix xsd: <http://www.w3.org/2001/XMLSchema#> .
case160:Company_B_Engineers_Project_Failure_Notification_to_Employer a proeth:ProjectSuccessFailureRiskEmployerNotificationObligation,
owl:NamedIndividual ;
rdfs:label "Company B Engineers Project Failure Notification to Employer" ;
proeth:casecontext "Company B engineers reviewed plans and specifications from Company A for machinery to be used in a manufacturing process, identified miscalculations and technical deficiencies, and notified their employer of their belief that the project would not be successful as designed." ;
proeth:compliancestatus "met" ;
proeth:conceptCategory "Obligation" ;
proeth:confidence "0.93" ;
proeth:derivedFromPrinciple case160:Faithful_Agent_Notification_Obligation_Fulfilled_by_Company_B_Engineers ;
proeth:discoveredincase "160" ;
proeth:discoveredinpass "2" ;
proeth:discoveredinsection "discussion" ;
proeth:firstdiscoveredat "2026-03-02T14:42:46.371997+00:00" ;
proeth:firstdiscoveredincase "160" ;
proeth:generatedattime "2026-03-02T14:42:46.371997+00:00" ;
proeth:importance "high" ;
proeth:obligatedparty "Engineers of Company B" ;
proeth:obligationclass "Project Success Failure Risk Employer Notification Obligation" ;
proeth:obligationstatement "Company B engineers were obligated to notify their employer that they did not believe the project would be successful as designed by Company A engineers, fulfilling their faithful agent obligation under Section 1(c) of the Code." ;
proeth:sourcetext "The engineers of Company 'B' fulfilled their obligation under Section l(c) of the Code by notifying their employer that they did not believe the project would be successful as designed by the engineers of Company 'A'" ;
proeth:temporalscope "Upon identification of miscalculations and technical deficiencies in Company A's plans and specifications, before proceeding with production" ;
proeth:textreferences "The engineers of Company 'B' fulfilled their obligation under Section l(c) of the Code by notifying their employer that they did not believe the project would be successful as designed by the engineers of Company 'A'" ;
proeth:wasattributedto "Case 160 Extraction" ;
prov:generatedAtTime "2026-03-02T14:53:01.002399"^^xsd:dateTime ;
prov:wasGeneratedBy "ProEthica Case 160 Extraction" .
Metadata
Extraction details
Discovered in case
160
Discovered in pass
2
Discovered in section
discussion
First discovered
2026-03-02T14:42:46.371997+00:00
First case
160
Generated
2026-03-02T14:42:46.371997+00:00
Attributed to
Case 160 Extraction
Generated
2026-03-02T14:53:01.002399
Generated by
ProEthica Case 160 Extraction