Engineer A Public Safety at Risk from Structural Failure
S · State
Individual
http://proethica.org/ontology/case/16#Engineer_A_Public_Safety_at_Risk_from_Structural_Failure
Properties
Instance of
Active period
From the structural failure through Engineer R's complete redesign of the structure
Affected parties
Contractor
Engineer A
Future occupants
Public
Confidence
0.95
Importance
high
Subject
The risk to public safety posed by Engineer B's deficient structural design, including portions of the structure not yet built at the time of the failure
Terminated by
Engineer R's complete redesign of the structure
Triggering event
Structural failure during basement construction and Engineer R's discovery of serious design errors in unbuilt portions of the structure
Urgency level
high
Source Evidence
Source text
Engineer R's review revealed a surprising number of serious structural design errors, omissions, and faulty details, not only for the failed basement, but also for the portions of the structure that had not been built yet
Text references
Engineer A retained Engineer R to completely redesign the structure
Engineer R's review revealed a surprising number of serious structural design errors, omissions, and faulty details, not only for the failed basement, but also for the portions of the structure that had not been built yet
TTL
@prefix case16: <http://proethica.org/ontology/case/16#> .
@prefix owl: <http://www.w3.org/2002/07/owl#> .
@prefix proeth: <http://proethica.org/ontology/intermediate#> .
@prefix prov: <http://www.w3.org/ns/prov#> .
@prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> .
@prefix xsd: <http://www.w3.org/2001/XMLSchema#> .
case16:Engineer_A_Public_Safety_at_Risk_from_Structural_Failure a proeth:PublicSafetyatRisk,
owl:NamedIndividual ;
rdfs:label "Engineer A Public Safety at Risk from Structural Failure" ;
proeth:activeperiod "From the structural failure through Engineer R's complete redesign of the structure" ;
proeth:affectedparties "Contractor",
"Engineer A",
"Future occupants",
"Public" ;
proeth:conceptCategory "State" ;
proeth:confidence "0.95" ;
proeth:discoveredincase "16" ;
proeth:discoveredinpass "1" ;
proeth:discoveredinsection "facts" ;
proeth:firstdiscoveredat "2026-02-25T04:09:06.505557+00:00" ;
proeth:firstdiscoveredincase "16" ;
proeth:generatedattime "2026-02-25T04:09:06.505557+00:00" ;
proeth:importance "high" ;
proeth:sourcetext "Engineer R's review revealed a surprising number of serious structural design errors, omissions, and faulty details, not only for the failed basement, but also for the portions of the structure that had not been built yet" ;
proeth:stateclass "Public Safety at Risk" ;
proeth:subject "The risk to public safety posed by Engineer B's deficient structural design, including portions of the structure not yet built at the time of the failure" ;
proeth:terminatedby "Engineer R's complete redesign of the structure" ;
proeth:textreferences "Engineer A retained Engineer R to completely redesign the structure",
"Engineer R's review revealed a surprising number of serious structural design errors, omissions, and faulty details, not only for the failed basement, but also for the portions of the structure that had not been built yet" ;
proeth:triggeringevent "Structural failure during basement construction and Engineer R's discovery of serious design errors in unbuilt portions of the structure" ;
proeth:urgencylevel "high" ;
proeth:wasattributedto "Case 16 Extraction" ;
prov:generatedAtTime "2026-02-25T12:12:21.730851"^^xsd:dateTime ;
prov:wasGeneratedBy "ProEthica Case 16 Extraction" .
Metadata
Extraction details
Discovered in case
16
Discovered in pass
1
Discovered in section
facts
First discovered
2026-02-25T04:09:06.505557+00:00
First case
16
Generated
2026-02-25T04:09:06.505557+00:00
Attributed to
Case 16 Extraction
Generated
2026-02-25T12:12:21.730851
Generated by
ProEthica Case 16 Extraction