Faithful Agent Obligation Present Case OPQ Construction

P · Principle Individual
http://proethica.org/ontology/case/140#Faithful_Agent_Obligation_Present_Case_OPQ_Construction
Properties
Instance of
FaithfulAgentObligationWithinEthicalLimits
http://proethica.org/ontology/intermediate#FaithfulAgentObligationWithinEthicalLimits
Applied to
Safety hazard notification to supervisor
Scaffolding design assignment for OPQ Construction
Balancing with
Proactive Risk Disclosure
Public Welfare Paramount
Concrete expression
Engineer A must execute the scaffolding design assignment diligently for OPQ Construction while retaining the professional authority and obligation to flag the commercial vehicle safety hazard before proceeding with design and assembly
Confidence
0.9
Importance
high
Interpretation
Faithful agent obligation requires Engineer A to proceed with the scaffolding design assignment while simultaneously discharging the professional obligation to notify the supervisor of the identified safety hazard
Invoked by
Engineer A Present Case OPQ Construction Scaffolding Designer
Tension resolution
The faithful agent obligation is fulfilled by proceeding with the assignment while proactively notifying the supervisor of the safety hazard, not by proceeding without notification
Source Evidence
Source text
appropriate corrective action can be considered and implemented prior to the design and assembly of the inspection and construction scaffolding by Engineer A and OPQ Construction

Text references
appropriate corrective action can be considered and implemented prior to the design and assembly of the inspection and construction scaffolding by Engineer A and OPQ Construction
prudent action would involve Engineer A immediately notifying verbally (and in writing if necessary) Engineer A's immediate supervisor at OPQ Construction of the safety hazards to employees (and others)
TTL
@prefix case140: <http://proethica.org/ontology/case/140#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proeth: <http://proethica.org/ontology/intermediate#> . @prefix prov: <http://www.w3.org/ns/prov#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix xsd: <http://www.w3.org/2001/XMLSchema#> . case140:Faithful_Agent_Obligation_Present_Case_OPQ_Construction a proeth:FaithfulAgentObligationWithinEthicalLimits, owl:NamedIndividual ; rdfs:label "Faithful Agent Obligation Present Case OPQ Construction" ; proeth:appliedto "Safety hazard notification to supervisor", "Scaffolding design assignment for OPQ Construction" ; proeth:balancingwith "Proactive Risk Disclosure", "Public Welfare Paramount" ; proeth:conceptCategory "Principle" ; proeth:concreteexpression "Engineer A must execute the scaffolding design assignment diligently for OPQ Construction while retaining the professional authority and obligation to flag the commercial vehicle safety hazard before proceeding with design and assembly" ; proeth:confidence "0.9" ; proeth:discoveredincase "140" ; proeth:discoveredinpass "2" ; proeth:discoveredinsection "discussion" ; proeth:firstdiscoveredat "2026-02-28T01:26:05.014062+00:00" ; proeth:firstdiscoveredincase "140" ; proeth:generatedattime "2026-02-28T01:26:05.014062+00:00" ; proeth:importance "high" ; proeth:interpretation "Faithful agent obligation requires Engineer A to proceed with the scaffolding design assignment while simultaneously discharging the professional obligation to notify the supervisor of the identified safety hazard" ; proeth:invokedby "Engineer A Present Case OPQ Construction Scaffolding Designer" ; proeth:principleclass "Faithful Agent Obligation Within Ethical Limits" ; proeth:sourcetext "appropriate corrective action can be considered and implemented prior to the design and assembly of the inspection and construction scaffolding by Engineer A and OPQ Construction" ; proeth:tensionresolution "The faithful agent obligation is fulfilled by proceeding with the assignment while proactively notifying the supervisor of the safety hazard, not by proceeding without notification" ; proeth:textreferences "appropriate corrective action can be considered and implemented prior to the design and assembly of the inspection and construction scaffolding by Engineer A and OPQ Construction", "prudent action would involve Engineer A immediately notifying verbally (and in writing if necessary) Engineer A's immediate supervisor at OPQ Construction of the safety hazards to employees (and others)" ; proeth:wasattributedto "Case 140 Extraction" ; prov:generatedAtTime "2026-02-28T01:40:09.762731"^^xsd:dateTime ; prov:wasGeneratedBy "ProEthica Case 140 Extraction" .
Metadata
Type
Individual
Last Updated
2026-05-28 16:27
Discovered in case
140
Discovered in pass
2
Discovered in section
discussion
First discovered
2026-02-28T01:26:05.014062+00:00
First case
140
Generated
2026-02-28T01:26:05.014062+00:00
Attributed to
Case 140 Extraction
Generated
2026-02-28T01:40:09.762731
Generated by
ProEthica Case 140 Extraction