Engineer A Funding Constraint Disclosure

O · Obligation Individual
http://proethica.org/ontology/case/14#Engineer_A_Funding_Constraint_Disclosure
Definition

Engineer A was obligated to disclose to City B Administrator all constraints imposed by the specific funding source on the available delivery methods, including the requirement that if Construction-Manager-at-Risk is selected, the Construction Manager at Risk firm and the Engineer of Record must be two distinct entities.

Properties
Instance of
FundingConstraintDisclosureObligation
http://proethica.org/ontology/intermediate#FundingConstraintDisclosureObligation
Case context
City B sought advice on delivery methods under a specific funding source that imposed constraints on how certain methods could be structured. Engineer A's memo omitted two of the four approved methods and did not address the funding agency's entity-separation requirement for Construction-Manager-at-Risk.
Compliance status
unmet
Confidence
0.86
Obligation statement
Engineer A was obligated to disclose to City B Administrator all constraints imposed by the specific funding source on the available delivery methods, including the requirement that if Construction-Manager-at-Risk is selected, the Construction Manager at Risk firm and the Engineer of Record must be two distinct entities.
Temporal scope
At the time of preparing and submitting the advisory memo to City B Administrator
Match Confidence
0.0
Matches Existing
false
Synthesis Literal
caseContext
complianceStatus
confidence
obligationClass
obligationStatement
temporalScope
textReferences
Relationships
obligatedParty Agent Engineer A
Source Evidence
Text references
Additionally, if Construction Manager at Risk is selected by the owner, City B, the funding agency requires the Construction Manager at Risk firm and the Engineer of Record be two distinct entities.
City B's City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a specific funding source.
Engineer A prepared a summary memo to City B Administrator and only identified Design-Bid-Build and Progressive-Design-Build as viable project delivery options.

Source text
City B's City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a specific funding source.
TTL
@prefix case14: <http://proethica.org/ontology/case/14#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proeth: <http://proethica.org/ontology/intermediate#> . @prefix proeth-core: <http://proethica.org/ontology/core#> . @prefix proeth-prov: <http://proethica.org/provenance#> . @prefix prov: <http://www.w3.org/ns/prov#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix skos: <http://www.w3.org/2004/02/skos/core#> . @prefix xsd: <http://www.w3.org/2001/XMLSchema#> . case14:Engineer_A_Funding_Constraint_Disclosure a proeth:FundingConstraintDisclosureObligation, owl:NamedIndividual ; rdfs:label "Engineer A Funding Constraint Disclosure" ; proeth-core:obligatedParty case14:Agent_Engineer_A ; proeth:caseContext "City B sought advice on delivery methods under a specific funding source that imposed constraints on how certain methods could be structured. Engineer A's memo omitted two of the four approved methods and did not address the funding agency's entity-separation requirement for Construction-Manager-at-Risk." ; proeth:complianceStatus "unmet" ; proeth:conceptCategory "Obligation" ; proeth:confidence "0.86" ; proeth:obligatedParty "Engineer A" ; proeth:obligationClass "Funding Constraint Disclosure Obligation" ; proeth:obligationStatement "Engineer A was obligated to disclose to City B Administrator all constraints imposed by the specific funding source on the available delivery methods, including the requirement that if Construction-Manager-at-Risk is selected, the Construction Manager at Risk firm and the Engineer of Record must be two distinct entities." ; proeth:temporalScope "At the time of preparing and submitting the advisory memo to City B Administrator" ; proeth:textReferences "Additionally, if Construction Manager at Risk is selected by the owner, City B, the funding agency requires the Construction Manager at Risk firm and the Engineer of Record be two distinct entities.", "City B's City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a specific funding source.", "Engineer A prepared a summary memo to City B Administrator and only identified Design-Bid-Build and Progressive-Design-Build as viable project delivery options." ; proeth-prov:discoveredInCase 14 ; proeth-prov:discoveredInPass 2 ; proeth-prov:discoveredInSection "facts" ; proeth-prov:firstDiscoveredAt "2026-06-04T08:44:38.157284+00:00"^^xsd:dateTime ; proeth-prov:firstDiscoveredInCase 14 ; proeth-prov:matchConfidence 0.0 ; proeth-prov:matchesExisting false ; proeth-prov:sourceText "City B's City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a specific funding source." ; proeth-prov:synthesisLiteral "caseContext", "complianceStatus", "confidence", "obligationClass", "obligationStatement", "temporalScope", "textReferences" ; rdfs:comment "Engineer A was obligated to disclose to City B Administrator all constraints imposed by the specific funding source on the available delivery methods, including the requirement that if Construction-Manager-at-Risk is selected, the Construction Manager at Risk firm and the Engineer of Record must be two distinct entities." ; skos:definition "Engineer A was obligated to disclose to City B Administrator all constraints imposed by the specific funding source on the available delivery methods, including the requirement that if Construction-Manager-at-Risk is selected, the Construction Manager at Risk firm and the Engineer of Record must be two distinct entities." ; prov:generatedAtTime "2026-06-04T08:44:38.157284+00:00"^^xsd:dateTime ; prov:wasAttributedTo "Case 14 Extraction", "claude-sonnet-4-6" ; prov:wasGeneratedBy "ProEthica Case 14 Extraction" .
Metadata
Type
Individual
Last Updated
2026-06-05 09:40
Discovered in case
14
Discovered in pass
2
Discovered in section
facts
First discovered
2026-06-04T08:44:38.157284+00:00
First case
14
Generated
2026-06-04T08:44:38.157284+00:00
Attributed to
['Case 14 Extraction', 'claude-sonnet-4-6']