Case context
Engineer B conducted the peer review while Engineer A's contract was still active; Engineer B accepted the successor design engineering contract only after Engineer A's agreement with the franchiser expired several weeks later.
Compliance status
met
Confidence
0.88
Importance
high
Obligated party
Engineer B
Obligation statement
Engineer B was obligated to refrain from accepting the successor design engineering contract from the franchiser until Engineer A's contract had fully expired, and was ethically permitted to accept the successor contract after that expiration given that Engineer B had fulfilled all collegial notification duties during the review phase.
Temporal scope
From the time of review engagement through the expiration of Engineer A's contract
Source Evidence
Source text
Several weeks later, Engineer A's agreement with the franchiser expires and the franchiser retains Engineer B as its design engineer

Text references
Several weeks later, Engineer A's agreement with the franchiser expires and the franchiser retains Engineer B as its design engineer
the franchiser begins discussions with Engineer B and retains Engineer B to provide immediate review of design concerns that are pending in connection with the design of several franchise facilities
TTL
@prefix case126: <http://proethica.org/ontology/case/126#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proeth: <http://proethica.org/ontology/intermediate#> . @prefix proeth-core: <http://proethica.org/ontology/core#> . @prefix prov: <http://www.w3.org/ns/prov#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix xsd: <http://www.w3.org/2001/XMLSchema#> . case126:Engineer_B_Successor_Contract_Acceptance_After_Engineer_A_Contract_Expiration a proeth:SuccessorEngineerPost-ReviewExpired-ContractAcceptancePermissibilityObligation, owl:NamedIndividual ; rdfs:label "Engineer B Successor Contract Acceptance After Engineer A Contract Expiration" ; proeth-core:defeasibleUnder <http://proethica.org/ontology/case/126#Client_Transition_Overlap_—_Franchiser_Dual_Engineer_Engagement> ; proeth:casecontext "Engineer B conducted the peer review while Engineer A's contract was still active; Engineer B accepted the successor design engineering contract only after Engineer A's agreement with the franchiser expired several weeks later." ; proeth:compliancestatus "met" ; proeth:conceptCategory "Obligation" ; proeth:confidence "0.88" ; proeth:derivedFromPrinciple case126:Successor_Engineer_Post-Review_Contract_Acceptance_Permissibility_Invoked_By_Engineer_B ; proeth:discoveredincase "126" ; proeth:discoveredinpass "2" ; proeth:discoveredinsection "facts" ; proeth:firstdiscoveredat "2026-03-01T10:15:07.500687+00:00" ; proeth:firstdiscoveredincase "126" ; proeth:generatedattime "2026-03-01T10:15:07.500687+00:00" ; proeth:importance "high" ; proeth:obligatedparty "Engineer B" ; proeth:obligationclass "Successor Engineer Post-Review Expired-Contract Acceptance Permissibility Obligation" ; proeth:obligationstatement "Engineer B was obligated to refrain from accepting the successor design engineering contract from the franchiser until Engineer A's contract had fully expired, and was ethically permitted to accept the successor contract after that expiration given that Engineer B had fulfilled all collegial notification duties during the review phase." ; proeth:sourcetext "Several weeks later, Engineer A's agreement with the franchiser expires and the franchiser retains Engineer B as its design engineer" ; proeth:temporalscope "From the time of review engagement through the expiration of Engineer A's contract" ; proeth:textreferences "Several weeks later, Engineer A's agreement with the franchiser expires and the franchiser retains Engineer B as its design engineer", "the franchiser begins discussions with Engineer B and retains Engineer B to provide immediate review of design concerns that are pending in connection with the design of several franchise facilities" ; proeth:wasattributedto "Case 126 Extraction" ; prov:generatedAtTime "2026-03-01T10:31:55.145742"^^xsd:dateTime ; prov:wasGeneratedBy "ProEthica Case 126 Extraction" .
Metadata
Type
Individual
Last Updated
2026-05-28 16:26
Discovered in case
126
Discovered in pass
2
Discovered in section
facts
First discovered
2026-03-01T10:15:07.500687+00:00
First case
126
Generated
2026-03-01T10:15:07.500687+00:00
Attributed to
Case 126 Extraction
Generated
2026-03-01T10:31:55.145742
Generated by
ProEthica Case 126 Extraction