Engineer A has identified the shortest workable route (saving 30 minutes from a two-hour trip) but this route requires addressing the impact to a historic family farmhouse. The engineer must present all alternatives, not merely the shortest route.
Compliance status
unclear
Confidence
0.89
Importance
high
Obligated party
Engineer A
Obligation statement
Engineer A is obligated to present the state with a complete comparative analysis of all workable route alternatives — including the shortest route requiring eminent domain of the historic farmhouse, longer routes avoiding the property, and any hybrid alternatives — with full analysis of travel time savings, property impacts, historic resource consequences, cost, and public welfare tradeoffs, so that the state can make a fully informed route selection decision.
Temporal scope
As part of the route specification deliverable under the state contract
Source Evidence
Source text
Engineer A determines that the shortest workable route would save approximately 30 minutes from what would otherwise be a two-hour trip.

Text references
Engineer A determines that the shortest workable route would save approximately 30 minutes from what would otherwise be a two-hour trip.
However, in order to build the shortest route, the state would be required to address the impact to a historic family farmhouse that has existed for over 100 years on the land required for the route.
TTL
@prefix case123: <http://proethica.org/ontology/case/123#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proeth: <http://proethica.org/ontology/intermediate#> . @prefix proeth-core: <http://proethica.org/ontology/core#> . @prefix prov: <http://www.w3.org/ns/prov#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix xsd: <http://www.w3.org/2001/XMLSchema#> . case123:Route_Alternative_Complete_Analysis_Engineer_A_JKL_State_Contract a proeth:RouteAlternativeCompleteComparativeAnalysisObligation, owl:NamedIndividual ; rdfs:label "Route Alternative Complete Analysis Engineer A JKL State Contract" ; proeth-core:defeasibleUnder case123:Competing_Route_Design_Approaches, case123:Engineer_A_Faithful_Agent_Boundary ; proeth:casecontext "Engineer A has identified the shortest workable route (saving 30 minutes from a two-hour trip) but this route requires addressing the impact to a historic family farmhouse. The engineer must present all alternatives, not merely the shortest route." ; proeth:compliancestatus "unclear" ; proeth:conceptCategory "Obligation" ; proeth:confidence "0.89" ; proeth:derivedFromPrinciple case123:Historic_Cultural_Resource_Impact_Invoked_By_Engineer_A_Farmhouse_Route, case123:Historic_and_Cultural_Resource_Impact_Consideration_Invoked_in_Route_Selection ; proeth:discoveredincase "123" ; proeth:discoveredinpass "2" ; proeth:discoveredinsection "facts" ; proeth:firstdiscoveredat "2026-02-28T00:00:48.240876+00:00" ; proeth:firstdiscoveredincase "123" ; proeth:generatedattime "2026-02-28T00:00:48.240876+00:00" ; proeth:importance "high" ; proeth:obligatedparty "Engineer A" ; proeth:obligationclass "Route Alternative Complete Comparative Analysis Obligation" ; proeth:obligationstatement "Engineer A is obligated to present the state with a complete comparative analysis of all workable route alternatives — including the shortest route requiring eminent domain of the historic farmhouse, longer routes avoiding the property, and any hybrid alternatives — with full analysis of travel time savings, property impacts, historic resource consequences, cost, and public welfare tradeoffs, so that the state can make a fully informed route selection decision." ; proeth:sourcetext "Engineer A determines that the shortest workable route would save approximately 30 minutes from what would otherwise be a two-hour trip." ; proeth:temporalscope "As part of the route specification deliverable under the state contract" ; proeth:textreferences "Engineer A determines that the shortest workable route would save approximately 30 minutes from what would otherwise be a two-hour trip.", "However, in order to build the shortest route, the state would be required to address the impact to a historic family farmhouse that has existed for over 100 years on the land required for the route." ; proeth:wasattributedto "Case 123 Extraction" ; prov:generatedAtTime "2026-02-28T00:14:43.750011"^^xsd:dateTime ; prov:wasGeneratedBy "ProEthica Case 123 Extraction" .
Metadata
Type
Individual
Last Updated
2026-05-28 16:26
Discovered in case
123
Discovered in pass
2
Discovered in section
facts
First discovered
2026-02-28T00:00:48.240876+00:00
First case
123
Generated
2026-02-28T00:00:48.240876+00:00
Attributed to
Case 123 Extraction
Generated
2026-02-28T00:14:43.750011
Generated by
ProEthica Case 123 Extraction