Legitimate Inter-Engineer Public Disagreement - Engineer C vs Engineers A and B

S · State Individual
http://proethica.org/ontology/case/113#Legitimate_Inter-Engineer_Public_Disagreement_-_Engineer_C_vs_Engineers_A_and_B
Properties
Instance of
LegitimateInter-EngineerPublicDisagreementState
http://proethica.org/ontology/intermediate#LegitimateInter-EngineerPublicDisagreementState
Active period
From Engineer C's first public contention, persisting through the unresolved controversy
Affected parties
Engineer A
Engineer B
Engineer C
Town Council
Town residents
Confidence
0.93
Importance
high
Subject
Engineer C's public technical and ethical challenge to the design decisions of Engineers A and B
Terminated by
Not terminated within the case facts
Triggering event
Engineer C publicly contending that the higher-level design concept is environmentally unsound and questioning whether Engineers A and B should have agreed to the higher intensity use
Urgency level
medium
Source Evidence
Source text
Engineer C, a resident of the town, publicly contends that the higher level design concept would be environmentally unsound

Text references
Engineer C has publicly questioned whether Engineers A and B should have agreed to the higher intensity use of the site
Engineer C, a resident of the town, publicly contends that the higher level design concept would be environmentally unsound
TTL
@prefix case113: <http://proethica.org/ontology/case/113#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proeth: <http://proethica.org/ontology/intermediate#> . @prefix prov: <http://www.w3.org/ns/prov#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix xsd: <http://www.w3.org/2001/XMLSchema#> . case113:Legitimate_Inter-Engineer_Public_Disagreement_-_Engineer_C_vs_Engineers_A_and_B a proeth:LegitimateInter-EngineerPublicDisagreementState, owl:NamedIndividual ; rdfs:label "Legitimate Inter-Engineer Public Disagreement - Engineer C vs Engineers A and B" ; proeth:activeperiod "From Engineer C's first public contention, persisting through the unresolved controversy" ; proeth:affectedparties "Engineer A", "Engineer B", "Engineer C", "Town Council", "Town residents" ; proeth:conceptCategory "State" ; proeth:confidence "0.93" ; proeth:discoveredincase "113" ; proeth:discoveredinpass "1" ; proeth:discoveredinsection "facts" ; proeth:firstdiscoveredat "2026-03-01T22:12:39.921562+00:00" ; proeth:firstdiscoveredincase "113" ; proeth:generatedattime "2026-03-01T22:12:39.921562+00:00" ; proeth:importance "high" ; proeth:sourcetext "Engineer C, a resident of the town, publicly contends that the higher level design concept would be environmentally unsound" ; proeth:stateclass "Legitimate Inter-Engineer Public Disagreement State" ; proeth:subject "Engineer C's public technical and ethical challenge to the design decisions of Engineers A and B" ; proeth:terminatedby "Not terminated within the case facts" ; proeth:textreferences "Engineer C has publicly questioned whether Engineers A and B should have agreed to the higher intensity use of the site", "Engineer C, a resident of the town, publicly contends that the higher level design concept would be environmentally unsound" ; proeth:triggeringevent "Engineer C publicly contending that the higher-level design concept is environmentally unsound and questioning whether Engineers A and B should have agreed to the higher intensity use" ; proeth:urgencylevel "medium" ; proeth:wasattributedto "Case 113 Extraction" ; prov:generatedAtTime "2026-03-01T22:37:07.044025"^^xsd:dateTime ; prov:wasGeneratedBy "ProEthica Case 113 Extraction" .
Metadata
Type
Individual
Last Updated
2026-05-28 16:26
Discovered in case
113
Discovered in pass
1
Discovered in section
facts
First discovered
2026-03-01T22:12:39.921562+00:00
First case
113
Generated
2026-03-01T22:12:39.921562+00:00
Attributed to
Case 113 Extraction
Generated
2026-03-01T22:37:07.044025
Generated by