Principal Engineer R Post-Error Risk Management Team Convening BWJ

O · Obligation Individual
http://proethica.org/ontology/case/11#Principal_Engineer_R_Post-Error_Risk_Management_Team_Convening_BWJ
Properties
Instance of
Post-ErrorRiskManagementTeamConveningObligation
http://proethica.org/ontology/intermediate#Post-ErrorRiskManagementTeamConveningObligation
Case context
Following confirmation of the stormwater design error, the BER directed that R should bring the BWJ risk management team together to address the runoff flow problem, conduct fault allocation, and ultimately develop and construct a corrective design serving the citizens of City C.
Compliance status
unclear
Confidence
0.87
Importance
high
Obligated party
Principal Engineer R
Obligation statement
Principal Engineer R was obligated, following acknowledgment of the stormwater runoff error, to convene the BWJ risk management team to collectively assess the error, determine fault allocation among all parties involved, and develop a workable corrective design that brings the subdivision into compliance with City C's regulatory requirements and eliminates the flooding harm to adjacent property owners.
Temporal scope
Following acknowledgment of the runoff problem and verification of IBM's analysis
Source Evidence
Source text
Engineer R of BWJ should consider obligations III.1.a and III.8, acknowledge the runoff problem, and bring the BWJ risk management team together to address the runoff flow problem.

Text references
Engineer R of BWJ should consider obligations III.1.a and III.8, acknowledge the runoff problem, and bring the BWJ risk management team together to address the runoff flow problem.
There may be a determination / allocation of fault by all parties involved.
Ultimately a workable design must be identified, designed, and constructed that serves the citizens of City C.
TTL
@prefix case11: <http://proethica.org/ontology/case/11#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proeth: <http://proethica.org/ontology/intermediate#> . @prefix prov: <http://www.w3.org/ns/prov#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix xsd: <http://www.w3.org/2001/XMLSchema#> . case11:Principal_Engineer_R_Post-Error_Risk_Management_Team_Convening_BWJ a proeth:Post-ErrorRiskManagementTeamConveningObligation, owl:NamedIndividual ; rdfs:label "Principal Engineer R Post-Error Risk Management Team Convening BWJ" ; proeth:casecontext "Following confirmation of the stormwater design error, the BER directed that R should bring the BWJ risk management team together to address the runoff flow problem, conduct fault allocation, and ultimately develop and construct a corrective design serving the citizens of City C." ; proeth:compliancestatus "unclear" ; proeth:conceptCategory "Obligation" ; proeth:confidence "0.87" ; proeth:derivedFromPrinciple case11:Professional_Accountability_Invoked_By_Principal_Engineer_R ; proeth:discoveredincase "11" ; proeth:discoveredinpass "2" ; proeth:discoveredinsection "discussion" ; proeth:firstdiscoveredat "2026-02-24T20:45:45.413800+00:00" ; proeth:firstdiscoveredincase "11" ; proeth:generatedattime "2026-02-24T20:45:45.413800+00:00" ; proeth:importance "high" ; proeth:obligatedparty "Principal Engineer R" ; proeth:obligationclass "Post-Error Risk Management Team Convening Obligation" ; proeth:obligationstatement "Principal Engineer R was obligated, following acknowledgment of the stormwater runoff error, to convene the BWJ risk management team to collectively assess the error, determine fault allocation among all parties involved, and develop a workable corrective design that brings the subdivision into compliance with City C's regulatory requirements and eliminates the flooding harm to adjacent property owners." ; proeth:sourcetext "Engineer R of BWJ should consider obligations III.1.a and III.8, acknowledge the runoff problem, and bring the BWJ risk management team together to address the runoff flow problem." ; proeth:temporalscope "Following acknowledgment of the runoff problem and verification of IBM's analysis" ; proeth:textreferences "Engineer R of BWJ should consider obligations III.1.a and III.8, acknowledge the runoff problem, and bring the BWJ risk management team together to address the runoff flow problem.", "There may be a determination / allocation of fault by all parties involved.", "Ultimately a workable design must be identified, designed, and constructed that serves the citizens of City C." ; proeth:wasattributedto "Case 11 Extraction" ; prov:generatedAtTime "2026-02-24T20:54:41.760291"^^xsd:dateTime ; prov:wasGeneratedBy "ProEthica Case 11 Extraction" .
Metadata
Type
Individual
Last Updated
2026-05-28 16:26
Discovered in case
11
Discovered in pass
2
Discovered in section
discussion
First discovered
2026-02-24T20:45:45.413800+00:00
First case
11
Generated
2026-02-24T20:45:45.413800+00:00
Attributed to
Case 11 Extraction
Generated
2026-02-24T20:54:41.760291
Generated by
ProEthica Case 11 Extraction