City C Municipal Infrastructure Client

R · Role Individual
http://proethica.org/ontology/case/11#City_C_Municipal_Infrastructure_Client
Definition

City C acting as the municipal authority that engaged third-party engineering firm IBM to review the subdivision design following flooding complaints, bearing authority over the review process and obligations to protect public welfare and investigate credible complaints of design deficiency and conflicts of interest.

Properties
Instance of
MunicipalInfrastructureClient
http://proethica.org/ontology/intermediate#MunicipalInfrastructureClient
Attributes
entity_typeMunicipal government
locationCity C, State Q
regulatory_roleSubdivision plan approval authority
Confidence
0.88
Importance
high
Relationships
typeclient_of
targetFirm IBM
typeemploys
targetCity Engineer J
typeregulatory_authority_over
targetDeveloper G
typeregulatory_authority_over
targetFirm BWJ
Role category
provider_client
Source Evidence
Source text
City C engaged a third-party engineering firm (IBM) to review the subdivision design

Text references
City C engaged a third-party engineering firm (IBM) to review the subdivision design
City C's subdivision regulations require that post-development 25-year recurrence interval peak stormwater flows must be equal to or less than pre-development conditions
TTL
@prefix case11: <http://proethica.org/ontology/case/11#> . @prefix owl: <http://www.w3.org/2002/07/owl#> . @prefix proeth: <http://proethica.org/ontology/intermediate#> . @prefix prov: <http://www.w3.org/ns/prov#> . @prefix rdfs: <http://www.w3.org/2000/01/rdf-schema#> . @prefix xsd: <http://www.w3.org/2001/XMLSchema#> . case11:City_C_Municipal_Infrastructure_Client a proeth:MunicipalInfrastructureClient, owl:NamedIndividual ; rdfs:label "City C Municipal Infrastructure Client" ; proeth:attributes "{'entity_type': 'Municipal government', 'location': 'City C, State Q', 'regulatory_role': 'Subdivision plan approval authority'}" ; proeth:caseinvolvement "City C acting as the municipal authority that engaged third-party engineering firm IBM to review the subdivision design following flooding complaints, bearing authority over the review process and obligations to protect public welfare and investigate credible complaints of design deficiency and conflicts of interest." ; proeth:conceptCategory "Role" ; proeth:confidence "0.88" ; proeth:discoveredincase "11" ; proeth:discoveredinpass "1" ; proeth:discoveredinsection "facts" ; proeth:firstdiscoveredat "2026-02-24T20:35:39.555288+00:00" ; proeth:firstdiscoveredincase "11" ; proeth:generatedattime "2026-02-24T20:35:39.555288+00:00" ; proeth:importance "high" ; proeth:relationships "{'type': 'client_of', 'target': 'Firm IBM'}", "{'type': 'employs', 'target': 'City Engineer J'}", "{'type': 'regulatory_authority_over', 'target': 'Developer G'}", "{'type': 'regulatory_authority_over', 'target': 'Firm BWJ'}" ; proeth:rolecategory "provider_client" ; proeth:roleclass "Municipal Infrastructure Client" ; proeth:sourcetext "City C engaged a third-party engineering firm (IBM) to review the subdivision design" ; proeth:textreferences "City C engaged a third-party engineering firm (IBM) to review the subdivision design", "City C's subdivision regulations require that post-development 25-year recurrence interval peak stormwater flows must be equal to or less than pre-development conditions" ; proeth:wasattributedto "Case 11 Extraction" ; prov:generatedAtTime "2026-02-24T20:54:41.750013"^^xsd:dateTime ; prov:wasGeneratedBy "ProEthica Case 11 Extraction" .
Metadata
Type
Individual
Last Updated
2026-05-28 16:26
Discovered in case
11
Discovered in pass
1
Discovered in section
facts
First discovered
2026-02-24T20:35:39.555288+00:00
First case
11
Generated
2026-02-24T20:35:39.555288+00:00
Attributed to
Case 11 Extraction
Generated
2026-02-24T20:54:41.750013
Generated by
ProEthica Case 11 Extraction